616 W 75TH ST 1-9 90044
Certificate Information: 616 W 75TH ST 1-9 90044
- Application / Permit
- 19016-10000-35251
- Plan Check / Job No.
- B19LA23292
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (3) SCCS.
- Permit Issued
- Issued on 6/30/2020
- Issuing Office
- Current Status
- CofC Issued on 10/23/2020
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2019 | VARAND SARKISIAN |
| Corrections Issued | 12/9/2019 | VARAND SARKISIAN |
| Quality Review Completed | 12/11/2019 | SAI KHUM |
| Plan Check Approved | 12/20/2019 | VARAND SARKISIAN |
| Issued | 6/30/2020 | APPLICANT |
| OK for CofC | 10/14/2020 | DARRYL ARNOLD |
| CofC Issued | 10/23/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 12/18/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 12/19/2019 | HELEN JADALI |
| Housing rent stabilization | Cleared | 4/23/2020 | STEVEN HOFSTAD |
Contact Information
| Architect | Miller,, Michael; Lic. No.: C26956 | 12756 MITCHELL AVE LOS ANGELES, CA 90066 |
| Contractor | Ark Construction Co; Lic. No.: 471822-B | 6131 SAN VICENTE BLVD LOS ANGELES, CA 90048 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/14/2020 | Approved | JOEY BUCHANAN |
| Special/Order Compliance | 8/14/2020 | Approved | JOEY BUCHANAN |
| Deputy Steel/Welding | 9/17/2020 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 9/30/2020 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 9/30/2020 | Approved | JOEY BUCHANAN |
| Wood Frame | 9/30/2020 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 10/1/2020 | No Access for Inspection | DARRYL ARNOLD |
| Wood Frame | 10/2/2020 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/8/2020 | Approved | DARRYL ARNOLD |
| Final | 10/14/2020 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 10/14/2020 | Approved | DARRYL ARNOLD |