9816 W WANDA PARK DR 90210
Certificate Information: 9816 W WANDA PARK DR 90210
- Application / Permit
- 19016-10000-35133
- Plan Check / Job No.
- B19LA23195
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED ALTERATION TO SINGLE FAMILY DWELLING TO CONVERT STORAGE ROOM TO RECREATION ROOM WITH HALF BATH ON 1ST FLOOR AND REMODEL 2ND FLOOR; WORK TO INCLUDE RECONFIGURING BATHROOM AND KITCHEN.
- Permit Issued
- Issued on 11/1/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2019 | SINA KHOSRAVI |
| Corrections Issued | 11/1/2019 | SINA KHOSRAVI |
| Issued | 11/1/2019 | LADBS |
| CofO in Progress | 4/7/2022 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
| CofO Issued | 4/15/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2019 | THOMAS LANG |
| Sewer availability | Cleared | 11/1/2019 | THOMAS LANG |
Contact Information
| Architect | Ryan,, Oonagh C; Lic. No.: C33156 | 923 E 3RD STREET #105 LOS ANGELES, CA 90013 |
| Contractor | Owner-Builder | , |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/28/2020 | Partial Approval | ANTHONY MCDOWALL |
| Pre-Inspection | 9/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 9/23/2020 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 10/13/2020 | Partial Approval | ANTHONY MCDOWALL |
| Sewer | 12/18/2020 | Partial Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2021 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 2/17/2021 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2021 | Partial Approval | ANTHONY MCDOWALL |
| Gas Test | 2/25/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Gas Test | 3/1/2021 | Partial Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 3/4/2021 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 4/8/2021 | Corrections Issued | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 4/13/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 4/15/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| HVAC-Rough | 4/19/2021 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 4/21/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2021 | Approved | ANTHONY MCDOWALL |
| HVAC-Rough | 4/27/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Drywall Nailing | 4/30/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 4/30/2021 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 5/28/2021 | Order to Comply Issued | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 6/28/2021 | Corrections Issued | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 7/2/2021 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 7/14/2021 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 8/20/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Rough | 8/24/2021 | Partial Approval | CHRISTOPHER WILSON |
| Service/Power Release | 8/26/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 10/14/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 1/13/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 1/21/2022 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Final | 1/21/2022 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/24/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 1/24/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 1/26/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 1/26/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 2/1/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 2/1/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/23/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Gas Test | 3/23/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/23/2022 | SGSOV Not Ready | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 3/23/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 3/31/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 3/31/2022 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 4/6/2022 | OK to Issue CofO | GERMAN RODRIGUEZ MENDOZA |