5921 E ECHO ST 90042
Certificate Information: 5921 E ECHO ST 90042
- Application / Permit
- 19016-10000-35110
- Plan Check / Job No.
- B19LA23172
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (6) Church
- Work Description
- ALTERATION/REPAIR TO EXISTING CHURCH
- Permit Issued
- Issued on 2/13/2023
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/29/2024
Permit Application Status History
| Submitted | 10/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SERGIO SILVA |
| Corrections Issued | 12/4/2019 | SERGIO SILVA |
| Green Plans Picked Up | 12/10/2019 | APPLICANT |
| Quality Review Completed | 12/11/2019 | KAMRAN GHOTBI RAVANDI |
| Disabled Access Plans Picked Up | 12/26/2019 | APPLICANT |
| Plan Check Approved | 7/1/2022 | SERGIO SILVA |
| Building Plans Picked Up | 7/5/2022 | APPLICANT |
| Issued | 2/13/2023 | APPLICANT |
| Permit Finaled | 3/29/2024 | RONALD JIMENEZ |
Permit Application Clearance Information
| Fire Marshall Fire Life Safety | Cleared | 12/24/2019 | PEJMAN NOORI |
| CPC | Cleared | 3/12/2020 | ANNA VIDAL |
| Miscellaneous | Cleared | 3/12/2020 | ANNA VIDAL |
| Specific Plan | Cleared | 3/12/2020 | ANNA VIDAL |
| ZA Case | Cleared | 3/12/2020 | ANNA VIDAL |
| ZA Case | Cleared | 3/12/2020 | ANNA VIDAL |
| HPOZ | Cleared | 3/18/2020 | AMANDA KAINER |
| ZI | Cleared | 3/18/2020 | AMANDA KAINER |
| Green Code | Cleared | 5/6/2022 | RICHARD GARCIA |
| DAS Clearance | Cleared | 5/25/2022 | EDDIE GARIN |
Contact Information
| Architect | Gonzalez,, Javier; Lic. No.: C25477 | 1090 W 11TH STREET APT 3 SAN PEDRO, CA 90731 |
| Contractor | Johnson Steel Source; Lic. No.: 797977-B | P O BOX 93292 PASADENA, CA 911093292 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/27/2023 | Approved | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 10/4/2023 | Conditional Approval | RAFAEL CORTES |
| Deputy Reinf. Concrete | 10/4/2023 | Conditional Approval | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 10/5/2023 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 10/13/2023 | No Access for Inspection | RAFAEL CORTES |
| Excavation/Setback/Form/Re-Bar | 10/17/2023 | Partial Approval | RAFAEL CORTES |
| Wood Frame | 12/5/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Interior/Exterior Lathing | 12/8/2023 | Partial Approval | JEROME BLACKWOOD |
| Insulation | 12/13/2023 | Approved | RAFAEL CORTES |
| Wood Frame | 12/13/2023 | Approved | RAFAEL CORTES |
| Drywall Nailing | 12/21/2023 | Approved | RAFAEL CORTES |
| T-Bar Ceiling | 1/19/2024 | Approved | RAMAZANALI ALMASI |
| Insulation | 2/16/2024 | Approved | RONALD JIMENEZ |
| Pre-Inspection | 2/16/2024 | Approved | RONALD JIMENEZ |
| Final | 3/20/2024 | Conditional Approval | RONALD JIMENEZ |
| Green Building Final | 3/20/2024 | Approved | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 3/20/2024 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 3/20/2024 | Approved | RONALD JIMENEZ |
| Final | 3/29/2024 | Permit Finaled | RONALD JIMENEZ |