16842 W DEVONSHIRE ST 91344

Certificate Information: 16842 W DEVONSHIRE ST 91344

Application / Permit
19016-10000-34886
Plan Check / Job No.
B19LA23026
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
TENANT IMPROVEMENT IN (E) BLDG, INCLUDING (N) PARTITIONS, CEILING POWER & FINISHES.
Permit Issued
Issued on 1/29/2020
Issuing Office
Metro
Current Status
Permit Finaled on 12/17/2020

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 11/8/2019 ZAW HAN
Corrections Issued 11/12/2019 ZAW HAN
Green Plans Picked Up 11/21/2019 APPLICANT
Quality Review Completed 12/5/2019 HERNAN ARREOLA
Disabled Access Plans Picked Up 12/5/2019 APPLICANT
Building Plans Picked Up 12/11/2019 APPLICANT
Plan Check Approved 1/23/2020 ZAW HAN
Issued 1/29/2020 LADBS
Permit Finaled 12/17/2020 JEFFREY FULTON

Permit Application Clearance Information

DAS Clearance Cleared 12/17/2019 SOMKIAT SUPANYACHOTSKUL
Eng Process Fee Ord 176,300 Cleared 1/2/2020 ERIK BEASLEY
Green Code Cleared 1/2/2020 ZAW HAN
Sewer availability Cleared 1/2/2020 ERIK BEASLEY

Contact Information

Architect Kamus,, John Howard; Lic. No.: C20397 5364 EVENING SKY DRIVE      SIMI VALLEY, CA 93063
Contractor Cirks Construction Inc; Lic. No.: 763589-B 1442 E LINCOLN AVENUE #334      ORANGE, CA 92865

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/30/2020 Partial Inspection JEFFREY FULTON
Deputy Drilled-In Anchors 2/4/2020 Conditional Approval JEFFREY FULTON
Deputy Reinf. Concrete 2/4/2020 Conditional Approval JEFFREY FULTON
Light Gage Steel Frame 2/7/2020 No Access for Inspection JEFFREY FULTON
Wood Frame 2/27/2020 Partial Inspection JEFFREY FULTON
Insulation 3/3/2020 Approved JEFFREY FULTON
Drywall Nailing 3/4/2020 Partial Inspection JEFFREY FULTON
Insulation 3/4/2020 Approved JEFFREY FULTON
T-Bar Ceiling 3/17/2020 Partial Inspection JEFFREY FULTON
T-Bar Ceiling 3/20/2020 Approved JEFFREY FULTON
T-Bar Ceiling 11/5/2020 Partial Inspection JEFFREY FULTON
Final 12/4/2020 Not Ready for Inspection JEFFREY FULTON
Green Building Final 12/4/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 12/4/2020 SGSOV Not Ready JEFFREY FULTON
Smoke Detectors 12/4/2020 Approved JEFFREY FULTON
Final 12/17/2020 Permit Finaled JEFFREY FULTON
Green Building Final 12/17/2020 Approved JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Approved JEFFREY FULTON