- Eplan 1274 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new moment frames.
- Permit Issued
- Issued on 7/20/2020
- Issuing Office
- Current Status
- CofC Issued on 6/21/2022
Permit Application Status History
| Submitted | 12/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/8/2020 | VARAND SARKISIAN |
| Corrections Issued | 1/14/2020 | VARAND SARKISIAN |
| Quality Review Completed | 1/26/2020 | HANS SANTIAGO |
| Plan Check Approved | 3/17/2020 | VARAND SARKISIAN |
| Issued | 7/20/2020 | APPLICANT |
| OK for CofC | 6/8/2022 | KENNETH ROBERTS |
| CofC Issued | 6/21/2022 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 4/22/2020 | MICHAEL GREGERSON |
Contact Information
| Architect | Santillan,, Michael; Lic. No.: C23337 | 832 SANTIAGO ROAD COSTA MESA, CA 92626 |
| Contractor | Henry Rob Construction; Lic. No.: 520770-B | 23655 WILDWOOD CANYON ROAD NEWHALL, CA 91321 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/1/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 1/21/2021 | Approved | JOE VELASQUEZ |
| Structural Steel Frame | 1/21/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 1/21/2021 | Partial Approval | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 2/4/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 2/5/2021 | Partial Approval | JOE VELASQUEZ |
| Wood Frame | 2/5/2021 | Partial Approval | JOE VELASQUEZ |
| Interior/Exterior Lathing | 4/5/2021 | Approved | JOE VELASQUEZ |
| Final | 5/7/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 5/7/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 1/31/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 1/31/2022 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 6/8/2022 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/8/2022 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 6/8/2022 | Approved | KENNETH ROBERTS |