6005 N FIGUEROA ST 90042

Certificate Information: 6005 N FIGUEROA ST 90042

Application / Permit
19016-10000-34852
Plan Check / Job No.
B19LA23015
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Office
Work Description
TENANT IMPROVEMENT, WITHIN EXISTING TENANT SPACE INCLUDING NEW PARTITIONS, CEILING POWER AND FINISHES. CHANGE OF USE FROM RETAIL TO MEDICAL OFFICE
Permit Issued
Issued on 2/5/2020
Issuing Office
Metro
Current Status
CofO Issued on 1/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 VU NGUYEN
Corrections Issued 11/13/2019 VU NGUYEN
Disabled Access Plans Picked Up 11/21/2019 APPLICANT
Quality Review Completed 11/26/2019 JOSE RODRIGUEZ
Building Plans Picked Up 12/3/2019 APPLICANT
Green Plans Picked Up 12/4/2019 APPLICANT
Applicant returned to address corrections 1/15/2020 VU NGUYEN
Plan Check Approved 1/21/2020 VU NGUYEN
Issued 2/5/2020 LADBS
CofO in Progress 1/25/2022 MARK FERRARI
CofO Issued 1/31/2022 TED RIES
Permit Finaled 1/31/2022 TED RIES

Permit Application Clearance Information

DAS Clearance Cleared 12/17/2019 SOMKIAT SUPANYACHOTSKUL
"Q" conditions Cleared 1/2/2020 TERRI OSBORNE
Green Code Cleared 1/2/2020 VU NGUYEN
ZA Case Cleared 1/2/2020 TERRI OSBORNE
Specific Plan Cleared 1/3/2020 KEVIN ARUCAN
HPOZ Cleared 1/14/2020 KATIE DEBIASE
Specific Plan Cleared 1/17/2020 ADRINEH MELKONIAN

Contact Information

No Data Available.

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/13/2020 Approved RONALD PACHECO
Green Building Rough 3/3/2020 Approved RONALD PACHECO
Light Gage Steel Frame 3/3/2020 Partial Approval RONALD PACHECO
Insulation 3/9/2020 Approved LEOPOLDO MENDOZA
Drywall Nailing 3/13/2020 Partial Approval RONALD PACHECO
T-Bar Ceiling 8/10/2020 Partial Approval RONALD PACHECO
Drywall Nailing 8/10/2021 Approved MARK FERRARI
Light Gage Steel Frame 8/10/2021 Approved MARK FERRARI
T-Bar Ceiling 8/10/2021 Approved MARK FERRARI
Final 8/20/2021 Not Ready for Inspection LANNY MERRICK
Green Building Final 8/20/2021 Not Ready for Inspection LANNY MERRICK
SGSOV-Seismic Gas S/O Valve 8/20/2021 SGSOV Approved LANNY MERRICK
Smoke Detectors 8/20/2021 Approved LANNY MERRICK
Wood Frame 8/20/2021 Approved LANNY MERRICK
Final 11/23/2021 Conditional Approval MARK FERRARI
Green Building Final 11/23/2021 Approved MARK FERRARI
Final 1/25/2022 OK to Issue CofO MARK FERRARI