1919 N ARGYLE AVE 90068

Certificate Information: 1919 N ARGYLE AVE 90068

Application / Permit
19016-10000-34792
Plan Check / Job No.
B19LA22982
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
NDC 409 NON-DUCTILE CONCRETE: FULL COMPLIANCE WITH NDC ORDINANCE: INTERIOR AND EXTERIOR RENOVATION OF AN EXISTING AFFORDABLE HOUSING COMPLEX FOR SENIORS. UPGRADES TO ACCESSIBILITY IN RESIDENTIAL UNITS AND COMMON AREAS. NEW LAYOUT TO COMMUNITY SPACES AND MANAGEMENT OFFICES. NEW GURNEY ELEVATOR TO REPLACE (1) NEW STRUCTURAL SUPPORTS AT BUILDING EXTERIOR AND ELEVATOR SHAFT
Permit Issued
Issued on 7/20/2020
Issuing Office
Current Status
Permit Finaled on 3/17/2023

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 LARRY LEE
Disabled Access Plans Picked Up 11/22/2019 APPLICANT
Corrections Issued 12/4/2019 LARRY LEE
Quality Review Completed 12/12/2019 CHARLES CHANG
Building Plans Picked Up 12/18/2019 APPLICANT
Applicant returned to address corrections 1/28/2020 LARRY LEE
Green Plans Picked Up 4/15/2020 APPLICANT
Applicant returned to address corrections 6/19/2020 LARRY LEE
Applicant returned to address corrections 6/23/2020 LARRY LEE
Applicant returned to address corrections 6/30/2020 LARRY LEE
Applicant returned to address corrections 7/1/2020 LARRY LEE
Applicant returned to address corrections 7/2/2020 LARRY LEE
Applicant returned to address corrections 7/9/2020 LARRY LEE
Plan Check Approved 7/10/2020 LARRY LEE
Issued 7/20/2020 APPLICANT
Permit Finaled 3/6/2023 TED RIES

Permit Application Clearance Information

Green Code Cleared 4/15/2020 VIVIAN LAO
DAS Clearance Cleared 6/15/2020 ELIZABETH TOMS
Fire Marshall Fire Life Safety Cleared 6/30/2020 ANDREW KO
Public Housing Cleared 7/9/2020 LUIS ALVAREZ

Contact Information

Contractor Walton Construction Inc; Lic. No.: 1034491-B 358 E FOOTHILL BLVD STE 100      SAN DIMAS, CA 91773

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2020 Approved RUSSELL BONVOULOIR
Light Gage Steel Frame 11/12/2020 Approved RUSSELL BONVOULOIR
Insulation 11/16/2020 Partial Approval RUSSELL BONVOULOIR
Insulation 11/24/2020 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 12/9/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/10/2020 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 12/11/2020 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 12/11/2020 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 12/14/2020 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 1/7/2021 Partial Approval EDWIN GREGORYONA
Pre-Inspection 1/25/2021 Partial Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 1/29/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 2/10/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/11/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/12/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 2/12/2021 Partial Approval RUSSELL BONVOULOIR
Pre-Inspection 2/12/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/16/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/18/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/19/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/22/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 2/23/2021 Conditional Approval RONALD PACHECO
Deputy Reinf. Concrete 2/24/2021 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 2/25/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 2/25/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 2/26/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/1/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 3/1/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/2/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 3/2/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/3/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/4/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/4/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/5/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/8/2021 Conditional Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 3/8/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/9/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/10/2021 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 3/10/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/11/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/12/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 3/16/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/17/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/18/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 3/19/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/23/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/24/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/25/2021 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 3/25/2021 Approved RUSSELL BONVOULOIR
Deputy Shotcrete 3/26/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/30/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 3/31/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/1/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/5/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/6/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/7/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/8/2021 Conditional Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 4/8/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/9/2021 Conditional Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 4/9/2021 Partial Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 4/9/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 4/12/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/12/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/14/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/15/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/16/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/19/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/20/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/22/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 4/23/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/26/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 4/26/2021 Partial Approval DAVID BURKHEAD
Deputy Shotcrete 4/27/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 4/28/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 4/29/2021 Conditional Approval DAVID BURKHEAD
Footing/Foundation/Slab 4/29/2021 Partial Inspection EDWIN GREGORYONA
Reinforced Concrete Frame 4/29/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 4/30/2021 Conditional Approval DAVID BURKHEAD
Deputy Shotcrete 5/3/2021 Conditional Approval DAVID BURKHEAD
Insulation 5/5/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Light Gage Steel Frame 5/5/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Reinforced Concrete Frame 5/5/2021 Not Ready for Inspection RUSSELL BONVOULOIR
Reinforced Concrete Frame 5/6/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Shotcrete 5/10/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Shotcrete 5/11/2021 Partial Approval EDWIN GREGORYONA
Deputy Shotcrete 5/12/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 5/12/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 5/12/2021 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 5/13/2021 Partial Approval RUSSELL BONVOULOIR
Reinforced Concrete Frame 5/13/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Shotcrete 5/17/2021 Partial Approval EDWIN GREGORYONA
Deputy Reinf. Concrete 5/19/2021 Partial Approval EDWIN GREGORYONA
Insulation 5/19/2021 Partial Approval DANIEL VARNUM
Light Gage Steel Frame 5/19/2021 Partial Approval DANIEL VARNUM
Footing/Foundation/Slab 5/20/2021 Partial Approval RUSSELL BONVOULOIR
Masonry Wall/Backfill 5/24/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Masonry 5/25/2021 Conditional Approval RUSSELL BONVOULOIR
Drywall Nailing 5/26/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 6/2/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 6/4/2021 Partial Approval EDWIN GREGORYONA
Deputy Drilled-In Anchors 6/7/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/7/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/8/2021 Partial Approval EDWIN GREGORYONA
Drywall Nailing 6/8/2021 Partial Approval RUSSELL BONVOULOIR
Insulation 6/8/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 6/8/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/9/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/10/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/10/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 6/10/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/11/2021 Conditional Approval RUSSELL BONVOULOIR
Special/Order Compliance 6/17/2021 Corrections Issued RUSSELL BONVOULOIR
Special/Order Compliance 6/25/2021 Corrections Issued RUSSELL BONVOULOIR
Deputy Reinf. Concrete 6/28/2021 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 6/30/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 7/12/2021 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 7/13/2021 Conditional Approval JONATHAN QUACH
Drywall Nailing 7/15/2021 Approved RUSSELL BONVOULOIR
Footing/Foundation/Slab 7/15/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/15/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Shotcrete 7/21/2021 Conditional Approval JONATHAN QUACH
Drywall Nailing 7/22/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/22/2021 Partial Approval RUSSELL BONVOULOIR
Drywall Nailing 7/26/2021 Partial Approval RUSSELL BONVOULOIR
Light Gage Steel Frame 7/26/2021 Partial Approval RUSSELL BONVOULOIR
Deputy Drilled-In Anchors 8/3/2021 Conditional Approval JONATHAN QUACH
Drywall Nailing 8/4/2021 Approved BRUCE CAMPBELL
Special/Order Compliance 8/4/2021 Conditional Approval BRUCE CAMPBELL
Deputy Steel/Welding 8/13/2021 Conditional Approval JONATHAN QUACH
Special/Order Compliance 9/8/2021 Partial Inspection RUSSELL BONVOULOIR
Pre-Inspection 9/22/2021 Approved RUSSELL BONVOULOIR
Deputy Reinf. Concrete 10/7/2021 Conditional Approval RUSSELL BONVOULOIR
Pre-Inspection 10/7/2021 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 10/8/2021 Approved SORIN CIRSTOIU
Light Gage Steel Frame 10/20/2021 Partial Approval SORIN CIRSTOIU
Deputy Shotcrete 10/21/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 10/22/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/26/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 10/26/2021 Approved SORIN CIRSTOIU
Drywall Nailing 10/26/2021 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 10/26/2021 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/27/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 10/27/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/28/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 10/28/2021 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 10/28/2021 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 10/29/2021 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 10/29/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 10/29/2021 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 11/1/2021 Partial Inspection SORIN CIRSTOIU
Footing/Foundation/Slab 11/1/2021 Partial Inspection SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/4/2021 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 11/4/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 11/4/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/5/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 11/5/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/8/2021 Conditional Approval RAFAEL ESPINOZA
Deputy Shotcrete 11/8/2021 Conditional Approval RAFAEL ESPINOZA
Excavation/Setback/Form/Re-Bar 11/8/2021 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 11/8/2021 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/9/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 11/9/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/10/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 11/10/2021 Approved SORIN CIRSTOIU
Deputy Drilled-In Anchors 11/12/2021 Approved SORIN CIRSTOIU
Deputy Shotcrete 11/12/2021 Approved SORIN CIRSTOIU
Footing/Foundation/Slab 11/15/2021 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 11/15/2021 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 11/18/2021 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 12/22/2021 Partial Approval SORIN CIRSTOIU
Special/Order Compliance 12/22/2021 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 12/27/2021 Partial Inspection SORIN CIRSTOIU
Insulation 12/27/2021 Partial Inspection SORIN CIRSTOIU
Special/Order Compliance 12/27/2021 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 12/29/2021 Partial Approval SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 12/29/2021 Partial Approval SORIN CIRSTOIU
Insulation 12/29/2021 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 12/30/2021 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 1/4/2022 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 1/5/2022 Order to Comply Issued SORIN CIRSTOIU
Drywall Nailing 1/5/2022 Partial Approval SORIN CIRSTOIU
Insulation 1/5/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 1/5/2022 Partial Approval SORIN CIRSTOIU
Deputy Shotcrete 1/6/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 1/7/2022 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/11/2022 Approved SORIN CIRSTOIU
Drywall Nailing 1/11/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 1/11/2022 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval SORIN CIRSTOIU
Footing/Foundation/Slab 1/13/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 1/19/2022 Partial Approval JONATHAN QUACH
Insulation 1/19/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 1/19/2022 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 1/26/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 1/26/2022 Partial Approval JONATHAN QUACH
Reinforced Concrete Frame 1/26/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 1/27/2022 Partial Approval JONATHAN QUACH
Light Gage Steel Frame 1/27/2022 Partial Approval JONATHAN QUACH
Drywall Nailing 2/2/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/11/2022 Approved SORIN CIRSTOIU
Drywall Nailing 2/17/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 2/17/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 2/22/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 2/23/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 2/24/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 2/25/2022 Approved SORIN CIRSTOIU
Special/Order Compliance 2/25/2022 Corrections Issued SORIN CIRSTOIU
Deputy Reinf. Concrete 2/28/2022 Conditional Approval JONATHAN QUACH
Drywall Nailing 2/28/2022 Partial Approval SORIN CIRSTOIU
Insulation 2/28/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/1/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/2/2022 Approved SORIN CIRSTOIU
Drywall Nailing 3/2/2022 Partial Approval SORIN CIRSTOIU
Special/Order Compliance 3/2/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/3/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/4/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/7/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/8/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/9/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/10/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/11/2022 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 3/11/2022 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 3/11/2022 Partial Inspection SORIN CIRSTOIU
Deputy Reinf. Concrete 3/14/2022 Conditional Approval JONATHAN QUACH
Deputy Shotcrete 3/14/2022 Conditional Approval JONATHAN QUACH
Excavation/Setback/Form/Re-Bar 3/14/2022 Partial Approval SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/14/2022 Partial Approval SORIN CIRSTOIU
Reinforced Concrete Frame 3/14/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/15/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/15/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/15/2022 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 3/16/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/16/2022 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/16/2022 Conditional Approval JONATHAN QUACH
Insulation 3/16/2022 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 3/16/2022 Partial Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/17/2022 Conditional Approval SORIN CIRSTOIU
Deputy Shotcrete 3/17/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/18/2022 Conditional Approval SORIN CIRSTOIU
Deputy Shotcrete 3/18/2022 Conditional Approval SORIN CIRSTOIU
Light Gage Steel Frame 5/12/2022 Partial Approval SORIN CIRSTOIU
Drywall Nailing 5/18/2022 Approved JONATHAN QUACH
Final 2/9/2023 No Access for Inspection TED RIES
Green Building Final 2/9/2023 No Access for Inspection TED RIES
SGSOV-Seismic Gas S/O Valve 2/9/2023 SGSOV Not Ready TED RIES
Smoke Detectors 2/9/2023 No Access for Inspection TED RIES
Final 2/13/2023 Partial Inspection TED RIES
Green Building Final 2/13/2023 Conditional Approval TED RIES
SGSOV-Seismic Gas S/O Valve 2/13/2023 SGSOV Approved TED RIES
Smoke Detectors 2/13/2023 Approved TED RIES
Final 3/6/2023 Permit Finaled TED RIES
Green Building Final 3/6/2023 Approved TED RIES