Pre-Inspection
|
9/15/2020
|
Approved
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
11/12/2020
|
Approved
|
RUSSELL BONVOULOIR
|
|
Insulation
|
11/16/2020
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Insulation
|
11/24/2020
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
12/9/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/10/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
12/11/2020
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
12/11/2020
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
12/14/2020
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
1/7/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Pre-Inspection
|
1/25/2021
|
Partial Approval
|
TIMOTHY BUXTON
|
|
Deputy Drilled-In Anchors
|
1/29/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
2/1/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
2/10/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/11/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/12/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
2/12/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
2/12/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/16/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/17/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/18/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/19/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/22/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
2/23/2021
|
Conditional Approval
|
RONALD PACHECO
|
|
Deputy Reinf. Concrete
|
2/24/2021
|
Conditional Approval
|
TIMOTHY BUXTON
|
|
Deputy Reinf. Concrete
|
2/25/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
2/25/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
2/26/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/1/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
3/1/2021
|
Not Ready for Inspection
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/2/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
3/2/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/3/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/4/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/4/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/5/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/8/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
3/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/9/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/10/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
3/10/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/11/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/12/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/15/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
3/16/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/17/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/17/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/18/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
3/19/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/23/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/24/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/25/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
3/25/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/26/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/30/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
3/31/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/1/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/5/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
4/6/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
4/7/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
4/8/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
4/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
4/9/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Excavation/Setback/Form/Re-Bar
|
4/9/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
4/9/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
4/12/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/12/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/14/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/15/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/16/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/19/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/20/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/22/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
4/23/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/26/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
4/26/2021
|
Partial Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
4/27/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
4/28/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
4/29/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Footing/Foundation/Slab
|
4/29/2021
|
Partial Inspection
|
EDWIN GREGORYONA
|
|
Reinforced Concrete Frame
|
4/29/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
4/30/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Deputy Shotcrete
|
5/3/2021
|
Conditional Approval
|
DAVID BURKHEAD
|
|
Insulation
|
5/5/2021
|
Not Ready for Inspection
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
5/5/2021
|
Not Ready for Inspection
|
RUSSELL BONVOULOIR
|
|
Reinforced Concrete Frame
|
5/5/2021
|
Not Ready for Inspection
|
RUSSELL BONVOULOIR
|
|
Reinforced Concrete Frame
|
5/6/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
5/10/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
5/11/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Shotcrete
|
5/12/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
5/12/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
5/12/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Excavation/Setback/Form/Re-Bar
|
5/13/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Reinforced Concrete Frame
|
5/13/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
5/17/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Reinf. Concrete
|
5/19/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Insulation
|
5/19/2021
|
Partial Approval
|
DANIEL VARNUM
|
|
Light Gage Steel Frame
|
5/19/2021
|
Partial Approval
|
DANIEL VARNUM
|
|
Footing/Foundation/Slab
|
5/20/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Masonry Wall/Backfill
|
5/24/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Masonry
|
5/25/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
5/26/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
6/2/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
6/4/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Deputy Drilled-In Anchors
|
6/7/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/7/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/8/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Drywall Nailing
|
6/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Insulation
|
6/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
6/8/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/9/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/10/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/10/2021
|
Partial Approval
|
EDWIN GREGORYONA
|
|
Footing/Foundation/Slab
|
6/10/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/11/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Special/Order Compliance
|
6/17/2021
|
Corrections Issued
|
RUSSELL BONVOULOIR
|
|
Special/Order Compliance
|
6/25/2021
|
Corrections Issued
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
6/28/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Footing/Foundation/Slab
|
6/30/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
7/12/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
7/13/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
7/15/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Footing/Foundation/Slab
|
7/15/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
7/15/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Shotcrete
|
7/21/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
7/22/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
7/22/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Drywall Nailing
|
7/26/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Light Gage Steel Frame
|
7/26/2021
|
Partial Approval
|
RUSSELL BONVOULOIR
|
|
Deputy Drilled-In Anchors
|
8/3/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
8/4/2021
|
Approved
|
BRUCE CAMPBELL
|
|
Special/Order Compliance
|
8/4/2021
|
Conditional Approval
|
BRUCE CAMPBELL
|
|
Deputy Steel/Welding
|
8/13/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Special/Order Compliance
|
9/8/2021
|
Partial Inspection
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
9/22/2021
|
Approved
|
RUSSELL BONVOULOIR
|
|
Deputy Reinf. Concrete
|
10/7/2021
|
Conditional Approval
|
RUSSELL BONVOULOIR
|
|
Pre-Inspection
|
10/7/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/8/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
10/20/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
10/21/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
10/22/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/26/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
10/26/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
10/26/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
10/26/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/27/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
10/27/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/28/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
10/28/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
10/28/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/28/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
10/29/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
10/29/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
10/29/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/1/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/1/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/4/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
11/4/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
11/4/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/5/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/5/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/8/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Deputy Shotcrete
|
11/8/2021
|
Conditional Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
11/8/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/8/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/8/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/9/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/9/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/10/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/10/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Drilled-In Anchors
|
11/12/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
11/12/2021
|
Approved
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/15/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
11/15/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
11/18/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
12/22/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Special/Order Compliance
|
12/22/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
12/27/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Insulation
|
12/27/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Special/Order Compliance
|
12/27/2021
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
12/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Excavation/Setback/Form/Re-Bar
|
12/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Insulation
|
12/29/2021
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
12/30/2021
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
1/4/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
1/5/2022
|
Order to Comply Issued
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
1/5/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Insulation
|
1/5/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
1/5/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
1/6/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
1/7/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/11/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
1/11/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
1/11/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
1/13/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Footing/Foundation/Slab
|
1/13/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
1/19/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Insulation
|
1/19/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Light Gage Steel Frame
|
1/19/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Deputy Drilled-In Anchors
|
1/26/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
1/26/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Reinforced Concrete Frame
|
1/26/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
1/27/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Light Gage Steel Frame
|
1/27/2022
|
Partial Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
2/2/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
2/11/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
2/17/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
2/17/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/22/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
2/23/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
2/24/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/25/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Special/Order Compliance
|
2/25/2022
|
Corrections Issued
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
2/28/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Drywall Nailing
|
2/28/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Insulation
|
2/28/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/1/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/2/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
3/2/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Special/Order Compliance
|
3/2/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/3/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
3/4/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
3/7/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/8/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/9/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/10/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/11/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/11/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
3/11/2022
|
Partial Inspection
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Shotcrete
|
3/14/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Excavation/Setback/Form/Re-Bar
|
3/14/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/14/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
3/14/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Reinforced Concrete Frame
|
3/14/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/15/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/15/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/15/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Deputy Reinf. Concrete
|
3/16/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/16/2022
|
Approved
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/16/2022
|
Conditional Approval
|
JONATHAN QUACH
|
|
Insulation
|
3/16/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
3/16/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/17/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/17/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Reinf. Concrete
|
3/18/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Deputy Shotcrete
|
3/18/2022
|
Conditional Approval
|
SORIN CIRSTOIU
|
|
Light Gage Steel Frame
|
5/12/2022
|
Partial Approval
|
SORIN CIRSTOIU
|
|
Drywall Nailing
|
5/18/2022
|
Approved
|
JONATHAN QUACH
|
|
Final
|
2/9/2023
|
No Access for Inspection
|
TED RIES
|
|
Green Building Final
|
2/9/2023
|
No Access for Inspection
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
2/9/2023
|
SGSOV Not Ready
|
TED RIES
|
|
Smoke Detectors
|
2/9/2023
|
No Access for Inspection
|
TED RIES
|
|
Final
|
2/13/2023
|
Partial Inspection
|
TED RIES
|
|
Green Building Final
|
2/13/2023
|
Conditional Approval
|
TED RIES
|
|
SGSOV-Seismic Gas S/O Valve
|
2/13/2023
|
SGSOV Approved
|
TED RIES
|
|
Smoke Detectors
|
2/13/2023
|
Approved
|
TED RIES
|
|
Final
|
3/6/2023
|
Permit Finaled
|
TED RIES
|
|
Green Building Final
|
3/6/2023
|
Approved
|
TED RIES
|