6821 1/2 S 11TH AVE 90043

Certificate Information: 6821 1/2 S 11TH AVE 90043

Application / Permit
19016-10000-34764
Plan Check / Job No.
B19LA22963
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AT REAR TO ACCESSORY DWELLING UNIT PER ORDINANCE.
Permit Issued
Issued on 5/19/2020
Issuing Office
Current Status
CofO Issued on 9/16/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 KEVIN MORALES
Corrections Issued 11/5/2019 KEVIN MORALES
Quality Review Completed 11/10/2019 YOUNG KIM
Building Plans Picked Up 11/15/2019 APPLICANT
Applicant returned to address corrections 4/1/2020 KEVIN MORALES
Green Plans Picked Up 4/9/2020 APPLICANT
Plan Check Approved 4/15/2020 KEVIN MORALES
Issued 5/19/2020 APPLICANT
CofO in Progress 9/14/2021 HORACE FULTZ
Permit Finaled 9/16/2021 DEROLD HAUFF
CofO Issued 9/16/2021 DEROLD HAUFF
Permit Finaled 9/16/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/13/2019 JEANIE LAM
CPC Cleared 11/13/2019 JOE LUCKEY
Eng Process Fee Ord 176,300 Cleared 11/13/2019 JEANIE LAM
Green Code Cleared 11/13/2019 VIVIAN LAO
Sewer availability Cleared 11/13/2019 JEANIE LAM
Project located in CRA area Cleared 11/15/2019 GISELLE CORELLA
Redevelopment Project Area Cleared 4/6/2020 DAVID URITA

Contact Information

Contractor Stay Forever Construction Corporation; Lic. No.: 986055-B 27138 CHERRY LAUREL PL      CANYON COUNTRY, CA 91387
Engineer Baraty,, Patrick; Lic. No.: S5900 1819 SUNSHINE COURT      GLENDALE, CA 91208

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/12/2020 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 6/24/2020 Approved FREDDIE RIVERA
ELECTRICAL-Rough 7/27/2020 Partial Approval JOSEPH MCGARRY
HVAC-Rough 7/27/2020 Not Ready for Inspection JOSEPH MCGARRY
Wood Frame 7/27/2020 Corrections Issued JOSEPH MCGARRY
Deputy Wood Construction 7/29/2020 Conditional Approval SABAS ALONSO
Green Building Rough 8/25/2020 Approved FREDDIE RIVERA
HVAC-Rough 8/25/2020 Partial Approval FREDDIE RIVERA
Interior/Exterior Lathing 8/25/2020 Not Ready for Inspection FREDDIE RIVERA
Wood Frame 8/25/2020 Approved FREDDIE RIVERA
Insulation 9/10/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 9/10/2020 Approved FREDDIE RIVERA
Drywall Nailing 9/17/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 11/18/2020 Approved FREDDIE RIVERA
Final 11/18/2020 Corrections Issued FREDDIE RIVERA
Green Building Final 11/18/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Approved FREDDIE RIVERA
Smoke Detectors 11/18/2020 Approved FREDDIE RIVERA
Final 11/25/2020 OK to Issue CofO FREDDIE RIVERA