9843 N MASON AVE 91311
Certificate Information: 9843 N MASON AVE 91311
- Application / Permit
- 19016-10000-34088
- Plan Check / Job No.
- B19LA22536
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- PROPOSED INTERIOR TENANT IMPROVEMENTS TO RESTAURANT AND ADD ROOF EQUIPMENTS
- Permit Issued
- Issued on 3/10/2020
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 9/30/2024
Permit Application Status History
| Submitted | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SINA KHOSRAVI |
| Corrections Issued | 11/5/2019 | SINA KHOSRAVI |
| Disabled Access Plans Picked Up | 11/8/2019 | APPLICANT |
| Green Plans Picked Up | 11/8/2019 | APPLICANT |
| Quality Review Completed | 11/10/2019 | YOUNG KIM |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Plan Check Approved | 3/4/2020 | SINA KHOSRAVI |
| No Progress | 3/4/2020 | SINA KHOSRAVI |
| Plan Check Approved | 3/4/2020 | SINA KHOSRAVI |
| Issued | 3/10/2020 | LADBS |
| Refund in Progress | 12/14/2020 | TERENCE SHIA |
| Refund Closed | 12/14/2020 | TERENCE SHIA |
| Issued | 12/14/2020 | TERENCE SHIA |
| Permit Finaled | 9/30/2024 | DEANDRE HOFFMAN |
Permit Application Clearance Information
| Food Service Establishment | Cleared | 1/16/2020 | RAMESHBHAIR PATEL |
| "D" conditions | Cleared | 1/29/2020 | JASON CHAN |
| "Q" conditions | Cleared | 1/29/2020 | JASON CHAN |
| Green Code | Cleared | 1/31/2020 | DONALD CRICHLOW |
| DAS Clearance | Cleared | 2/3/2020 | CHOI YAN |
| Food establishment approval | Cleared | 3/4/2020 | LACDHS APPROVED |
Contact Information
| Architect | Amor,, William Andrew; Lic. No.: C24421 | 9483 HAVEN AVENUE RANCHO CUCAMONGA, CA 91730 |
| Contractor | B N C Industries Inc; Lic. No.: 1024294-B | P O BOX 5609 SANTA MARIA, CA 93456 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 5/14/2020 | Corrections Issued | ROBERT COLE |
| Light Gage Steel Frame | 5/26/2020 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 5/28/2020 | Approved | JEFFREY FULTON |
| Grading Pre-Inspection | 9/1/2020 | Partial Inspection | JEFFREY FULTON |
| Grading Pre-Inspection | 9/4/2020 | Partial Inspection | JEFFREY FULTON |
| Final | 10/26/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 11/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 11/5/2020 | Not Ready for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 11/5/2020 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 11/5/2020 | Approved | JEFFREY FULTON |
| Final | 11/9/2020 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 9/30/2024 | Permit Finaled | DEANDRE HOFFMAN |
| Green Building Final | 9/30/2024 | Approved | DEANDRE HOFFMAN |