2149 W BAXTER ST 90039
Certificate Information: 2149 W BAXTER ST 90039
- Application / Permit
- 19016-10000-33938
- Plan Check / Job No.
- B19LA22435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 2 SCCS.
- Permit Issued
- Issued on 1/7/2021
- Issuing Office
- Current Status
- CofC Issued on 3/16/2021
Permit Application Status History
| Submitted | 10/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | CHUNG-WEN CHUANG |
| Corrections Issued | 11/25/2019 | CHUNG-WEN CHUANG |
| Quality Review Completed | 12/1/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Applicant returned to address corrections | 12/30/2019 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/7/2020 | CHUNG-WEN CHUANG |
| Plan Check Approved | 4/8/2020 | CHUNG-WEN CHUANG |
| Issued | 1/7/2021 | APPLICANT |
| OK for CofC | 3/12/2021 | MARK FERRARI |
| CofC Issued | 3/16/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | BOK GOH |
| Work Adjacent to Public Way | Cleared | 1/24/2020 | DANNY MORALES |
| Housing rent stabilization | Cleared | 1/6/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2021 | Approved | MARK FERRARI |
| Wood Frame | 2/18/2021 | Partial Approval | MARK FERRARI |
| Deputy Drilled-In Anchors | 2/23/2021 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 3/2/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 3/3/2021 | Approved | MARK FERRARI |
| Structural Steel Frame | 3/3/2021 | Approved | MARK FERRARI |
| Wood Frame | 3/3/2021 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 3/4/2021 | Conditional Approval | MARK FERRARI |
| Insulation | 3/8/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 3/8/2021 | Approved | MARK FERRARI |
| Final | 3/12/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV No Gas | MARK FERRARI |
| Smoke Detectors | 3/12/2021 | Approved | MARK FERRARI |