930 N WHITE KNOLL DR 90012
Certificate Information: 930 N WHITE KNOLL DR 90012
- Application / Permit
- 19016-10000-33928
- Plan Check / Job No.
- B19LA22427
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 2/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/10/2021
Permit Application Status History
| Submitted | 10/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | MANUEL MONTUFAR |
| Corrections Issued | 12/2/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/9/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/10/2020 | MANUEL MONTUFAR |
| Issued | 2/27/2020 | LADBS |
| OK for CofC | 2/9/2021 | MARK FERRARI |
| CofC Issued | 2/10/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 2/18/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Bc7 Construction Inc; Lic. No.: 1049615-B | 962 E 6TH STREET ONTARIO, CA 91764 |
| Engineer | Gao,, Jianfeng; Lic. No.: C88478 | 833 E MOBECK ST APT C WEST COVINA, CA 91790 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/13/2020 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 7/15/2020 | Approved | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 7/15/2020 | Partial Approval | MARK FERRARI |
| Pre-Inspection | 8/12/2020 | Partial Inspection | MARK FERRARI |
| Pre-Inspection | 8/17/2020 | Corrections Issued | VAHE KELEDJIAN |
| Deputy Steel/Welding | 9/4/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/15/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 9/16/2020 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/17/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 10/1/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/1/2020 | Corrections Issued | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/14/2020 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 10/19/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 10/23/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 11/20/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 12/3/2020 | No Access for Inspection | MARK FERRARI |
| Drywall Nailing | 12/9/2020 | Approved | DARRYL ARNOLD |
| Final | 12/29/2020 | Corrections Issued | MARK FERRARI |
| METHANE-Final | 12/29/2020 | Approved | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 12/29/2020 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 12/29/2020 | Not Ready for Inspection | MARK FERRARI |
| Final | 1/26/2021 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 1/26/2021 | Approved | MARK FERRARI |
| Final | 2/9/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Approved | MARK FERRARI |