2808 N WORKMAN ST #1-4 90031
Certificate Information: 2808 N WORKMAN ST #1-4 90031
- Application / Permit
- 19016-10000-33895
- Plan Check / Job No.
- B19LA22411
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT SINGLE FAMILY DWELLING TO 3 UNITS AND AN ADU. ENCLOSED (E) PORCHES ON THE REAR @ GROUND 2nd FLOOR LEVEL AND REMODELING. All work per engr's details
- Permit Issued
- Issued on 2/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SAM CHANG |
| Disabled Access Plans Picked Up | 11/5/2019 | APPLICANT |
| Corrections Issued | 11/8/2019 | SAM CHANG |
| Quality Review Completed | 11/9/2019 | STANLEY RAAP |
| Applicant returned to address corrections | 1/21/2021 | SAM CHANG |
| Applicant returned to address corrections | 3/10/2021 | SAM CHANG |
| Applicant returned to address corrections | 4/22/2021 | SAM CHANG |
| Applicant returned to address corrections | 8/26/2021 | SAM CHANG |
| Applicant returned to address corrections | 1/4/2022 | SAM CHANG |
| Plan Check Approved | 1/5/2022 | SAM CHANG |
| Issued | 2/25/2022 | APPLICANT |
| Building Plans Picked Up | 2/28/2022 | APPLICANT |
| CofO in Progress | 1/3/2024 | RAFAEL CORTES |
| Permit Finaled | 1/3/2024 | ERNESTO CORRAL |
| CofO Issued | 1/3/2024 | ERNESTO CORRAL |
| Permit Finaled | 1/3/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 11/18/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/14/2020 | EMIL KYUPELYAN |
| CPC | Cleared | 1/22/2020 | TERRI OSBORNE |
| CPC | Cleared | 1/22/2020 | TERRI OSBORNE |
| HPOZ | Cleared | 1/20/2021 | JONATHAN KAPLAN |
| ZI | Cleared | 1/20/2021 | JONATHAN KAPLAN |
| DAS Clearance | Cleared | 4/29/2021 | CHOI YAN |
| Housing rent stabilization | Cleared | 10/21/2021 | ISMAEL HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 12/3/2021 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 12/8/2021 | JOHN CONNEALLY |
| Green Code | Cleared | 12/21/2021 | AARON COSTA |
Contact Information
| Contractor | Smart Remodeling; Lic. No.: 953573-B | 1675 AMBERWOOD DR 25 SOUTH PASADENA, CA 91030 |
| Engineer | Lopez,, Mauricio Jose; Lic. No.: C36801 | 1391 N THIRD AVE UPLAND, CA 91786 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2022 | Partial Inspection | MARK FERRARI |
| Pre-Inspection | 3/1/2022 | Corrections Issued | MARK FERRARI |
| Wood Frame | 3/1/2022 | Not Ready for Inspection | MARK FERRARI |
| Deputy Drilled-In Anchors | 3/3/2022 | Conditional Approval | MARK FERRARI |
| Wood Frame | 3/10/2022 | Partial Inspection | MARK FERRARI |
| Wood Frame | 3/29/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 4/19/2022 | Partial Approval | BRUCE CAMPBELL |
| Drywall Nailing | 4/26/2022 | Partial Approval | MARK FERRARI |
| Wood Frame | 5/10/2022 | Partial Approval | MARK FERRARI |
| Drywall Nailing | 6/3/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 6/3/2022 | Corrections Issued | MARK FERRARI |
| Drywall Nailing | 7/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 7/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 7/8/2022 | Not Ready for Inspection | MARK FERRARI |
| Deputy Wood Construction | 7/18/2022 | Conditional Approval | WINSTON DUNNING |
| Deputy Wood Construction | 7/21/2022 | Conditional Approval | WINSTON DUNNING |
| Insulation | 7/22/2022 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 7/28/2022 | Not Ready for Inspection | MARK FERRARI |
| Drywall Nailing | 8/1/2022 | Approved | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 8/1/2022 | Not Ready for Inspection | MARK FERRARI |
| Interior/Exterior Lathing | 8/5/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/17/2022 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | MARK FERRARI |
| Wood Frame | 8/17/2022 | Not Ready for Inspection | MARK FERRARI |
| Final | 12/18/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 12/18/2023 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 12/18/2023 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 12/18/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 12/18/2023 | Approved | RAFAEL CORTES |
| Final | 12/26/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Smoke Detectors | 12/26/2023 | Approved | RAFAEL CORTES |
| Final | 1/2/2024 | OK to Issue CofO | RAFAEL CORTES |