1423 N FULLER AVE 90046
Certificate Information: 1423 N FULLER AVE 90046
- Application / Permit
- 19016-10000-33759
- Plan Check / Job No.
- B19LA22331
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 1222 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new SCCS.
- Permit Issued
- Issued on 2/5/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 6/24/2020
Permit Application Status History
| Submitted | 10/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | VARAND SARKISIAN |
| Corrections Issued | 12/2/2019 | VARAND SARKISIAN |
| Quality Review Completed | 12/13/2019 | HANS SANTIAGO |
| Plan Check Approved | 1/13/2020 | VARAND SARKISIAN |
| Issued | 2/5/2020 | LADBS |
| OK for CofC | 6/24/2020 | MARK FERRARI |
| CofC Issued | 6/24/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 1/31/2020 | CHARLES GARCIA |
Contact Information
| Contractor | Ces4 Construction; Lic. No.: 1042127-B | 19562 VENTURA BLVD UNIT 238 TARZANA, CA 91356 |
| Engineer | Zohrevand,, Pedram; Lic. No.: C82328 | 21201 KITTRIDGE ST APT 9105 WOODLAND HILLS, CA 91303 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/3/2020 | Approved | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 3/17/2020 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 3/18/2020 | Approved | BRUCE CAMPBELL |
| Wood Frame | 3/18/2020 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 3/20/2020 | No Access for Inspection | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 3/24/2020 | Conditional Approval | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 3/31/2020 | Corrections Issued | FELIX CEBALLOS |
| Interior/Exterior Lathing | 4/2/2020 | Corrections Issued | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2020 | SGSOV Not Ready | FELIX CEBALLOS |
| Final | 4/21/2020 | Partial Inspection | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2020 | SGSOV Approved | FELIX CEBALLOS |
| Smoke Detectors | 4/21/2020 | Approved | FELIX CEBALLOS |
| Final | 6/24/2020 | OK for CofC | MARK FERRARI |