1635 S STONER AVE 90025

Certificate Information: 1635 S STONER AVE 90025

Application / Permit
19016-10000-33290
Plan Check / Job No.
B19LA22063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
MANDATORY SOFT STORY RETROFIT AS PER LABC CHAPTER 93. REMOVE EXISTING TWO COLUMNS AND INSTALL TWO (N) SCCS. NO CHANGE IN PARKING OR LAY-OUT.
Permit Issued
Issued on 2/15/2022
Issuing Office
Current Status
CofC Issued on 10/19/2022

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 11/20/2019 JOHN FRANCIA
Corrections Issued 11/25/2019 JOHN FRANCIA
Quality Review Completed 12/1/2019 HANS SANTIAGO
Building Plans Picked Up 12/5/2019 APPLICANT
Plan Check Approved 12/1/2021 JOHN FRANCIA
Issued 2/15/2022 APPLICANT
OK for CofC 9/28/2022 PAUL DAVIDSON
CofC Issued 10/19/2022 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 12/17/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 12/17/2019 ERIK BEASLEY
Housing rent stabilization Cleared 2/10/2022 MICHAEL SOTO

Contact Information

Contractor Cal Retrofit; Lic. No.: 1022167-B 19528 VENTURA BLVD #300      TARZANA, CA 91356
Engineer Zohrevand,, Pedram; Lic. No.: C82328 21201 KITTRIDGE ST APT 9105      WOODLAND HILLS, CA 91303

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2022 Approved ALAN NOVAK
Deputy Reinf. Concrete 4/14/2022 Conditional Approval JOHN DODGE
Deputy Other (see comments) 4/15/2022 Approved JOHN DODGE
Deputy Reinf. Concrete 4/15/2022 Approved JOHN DODGE
Footing/Foundation/Slab 5/5/2022 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 5/6/2022 Conditional Approval JOHN DODGE
Footing/Foundation/Slab 5/24/2022 Partial Approval JOHN DODGE
Deputy Reinf. Concrete 5/25/2022 Conditional Approval JOHN DODGE
Deputy Steel/Welding 5/27/2022 Conditional Approval JOHN DODGE
Deputy Other (see comments) 5/31/2022 Conditional Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 6/9/2022 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 6/9/2022 Conditional Approval SORIN CIRSTOIU
Footing/Foundation/Slab 6/15/2022 Approved SORIN CIRSTOIU
Structural Steel Frame 6/15/2022 Approved SORIN CIRSTOIU
Wood Frame 6/15/2022 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 6/16/2022 Conditional Approval SORIN CIRSTOIU
Interior/Exterior Lathing 6/23/2022 Approved SORIN CIRSTOIU
Final 9/22/2022 Not Ready for Inspection ALAN NOVAK
SGSOV-Seismic Gas S/O Valve 9/22/2022 SGSOV Approved ALAN NOVAK
Smoke Detectors 9/22/2022 Approved ALAN NOVAK
Final 9/28/2022 OK for CofC PAUL DAVIDSON