3567 3/4 E SABINA ST 90023

Certificate Information: 3567 3/4 E SABINA ST 90023

Application / Permit
19016-10000-33262
Plan Check / Job No.
B19LA22046
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO ADU per CA GOVt. Code 65852.2(e)(1)(D).
Permit Issued
Issued on 9/3/2020
Issuing Office
Metro
Current Status
CofO Issued on 8/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 SAMUEL GONZALEZ
Corrections Issued 11/21/2019 SAMUEL GONZALEZ
Quality Review Completed 12/10/2019 LAWRENCE QUIRANTE
Building Plans Picked Up 12/27/2019 APPLICANT
Plan Check Approved 8/17/2020 SAMUEL GONZALEZ
Issued 9/3/2020 APPLICANT
CofO in Progress 7/22/2021 ROBERT VORHIS
CofO Issued 8/26/2022 DEROLD HAUFF
Permit Finaled 8/26/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/12/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/12/2020 CELINA MORENO
Sewer availability Cleared 2/12/2020 THOMAS LANG
ZI Cleared 2/26/2020 RICHARD REASER
DAS Clearance Cleared 8/12/2020 SAMUEL GONZALEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/4/2020 Conditional Approval RONALD PACHECO
Pre-Inspection 12/4/2020 Not Ready for Inspection RONALD PACHECO
Footing/Foundation/Slab 12/8/2020 Corrections Issued RONALD PACHECO
Deputy Drilled-In Anchors 12/24/2020 Conditional Approval DANIEL COLLINS
Wood Frame 1/4/2021 Partial Approval LANNY MERRICK
Interior/Exterior Lathing 1/7/2021 Approved LANNY MERRICK
Pre-Inspection 2/9/2021 Partial Approval ROBERT VORHIS
Pre-Inspection 3/24/2021 Partial Inspection ROBERT VORHIS
Pre-Inspection 4/7/2021 Partial Inspection ROBERT VORHIS
Insulation 4/13/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Insulation 4/26/2021 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/7/2021 Approved ROBERT VORHIS
Final 6/23/2021 Corrections Issued ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 6/23/2021 SGSOV Approved ROBERT VORHIS
Smoke Detectors 6/23/2021 Approved ROBERT VORHIS
Wood Frame 6/23/2021 Approved ROBERT VORHIS
Final 7/22/2021 OK to Issue CofO ROBERT VORHIS
Special/Order Compliance 7/23/2021 Corrections Issued ROBERT VORHIS