6301 W 3RD ST BLDG N 90036

Certificate Information: 6301 W 3RD ST BLDG N 90036

Application / Permit
19016-10000-33250
Plan Check / Job No.
B19LA22036
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Storage Building
Work Description
DEMOLITION OF PART OF (E) TWO STORY BUILDING. CHANGE OF USE FROM RETAIL TO STORAGE BUILDING.
Permit Issued
Issued on 2/13/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Green Plans Picked Up 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 KEVIN MORALES
Corrections Issued 11/1/2019 KEVIN MORALES
Disabled Access Plans Picked Up 11/7/2019 APPLICANT
Quality Review Completed 11/9/2019 YOUNG KIM
Building Plans Picked Up 11/18/2019 APPLICANT
Plan Check Approved 12/10/2019 KEVIN MORALES
Issued 2/13/2020 LADBS
CofO Issued 6/17/2024 WINSTON DUNNING
Permit Finaled 6/17/2024 WINSTON DUNNING

Permit Application Clearance Information

"D" conditions Cleared 11/26/2019 ANNA VAN
"T" removal Cleared 11/26/2019 ANNA VAN
ZA Case Cleared 11/26/2019 ANNA VAN
ZI Cleared 11/26/2019 ANNA VAN
Green Code Cleared 12/3/2019 KHEDER ALRAZAA
DAS Clearance Cleared 12/10/2019 SOMKIAT SUPANYACHOTSKUL

Contact Information

Contractor Whiting-Turner Contracting Company The; Lic. No.: 311107-B 800 R STREET      SACRAMENTO, CA 95811
Engineer Stewart,, Joseph Eugene; Lic. No.: S3065 4117 MEADOW LARK DR      CALABASAS, CA 91302

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Green Building Rough 3/5/2020 Not Ready for Inspection TIMOTHY BUXTON
METHANE-Rough 3/5/2020 Not Ready for Inspection TIMOTHY BUXTON
Wood Frame 3/5/2020 Partial Approval TIMOTHY BUXTON
Green Building Rough 4/21/2020 Approved JONATHAN QUACH
METHANE-Rough 4/21/2020 Approved JONATHAN QUACH
Wood Frame 4/21/2020 Approved JONATHAN QUACH
Floor/Roof Diaphrgm/Shear Wall 4/23/2020 Partial Approval TIMOTHY BUXTON
Deputy Methane Barrier 5/26/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 5/28/2020 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/28/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 5/29/2020 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/29/2020 Conditional Approval TIMOTHY BUXTON
Deputy Drilled-In Anchors 6/1/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 6/1/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 6/2/2020 Approved JONATHAN QUACH
Deputy Reinf. Concrete 6/2/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 6/2/2020 Partial Approval JONATHAN QUACH
Deputy Drilled-In Anchors 6/3/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 6/3/2020 Conditional Approval JONATHAN QUACH
Pre-Inspection 6/12/2020 Partial Inspection JONATHAN QUACH
Drywall Nailing 6/17/2020 Not Ready for Inspection JONATHAN QUACH
Deputy Methane Barrier 6/19/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 7/16/2020 Conditional Approval JONATHAN QUACH
Deputy Methane Barrier 7/17/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 8/25/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 8/25/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 8/26/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 8/26/2020 Conditional Approval JONATHAN QUACH
Deputy Drilled-In Anchors 8/27/2020 Conditional Approval JONATHAN QUACH
Deputy Reinf. Concrete 8/27/2020 Conditional Approval JONATHAN QUACH
Light Gage Steel Frame 9/30/2020 Partial Approval TIMOTHY BUXTON
Drywall Nailing 10/7/2020 Partial Approval TIMOTHY BUXTON
Final 1/24/2024 Partial Inspection JACOB MYERS
Green Building Final 1/24/2024 Partial Approval JACOB MYERS
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Approved JACOB MYERS
Smoke Detectors 1/24/2024 Partial Inspection JACOB MYERS
Final 6/17/2024 Conditional Approval WINSTON DUNNING
Green Building Final 6/17/2024 Approved WINSTON DUNNING
Smoke Detectors 6/17/2024 Approved WINSTON DUNNING