2400 N HYPERION AVE 90027

Certificate Information: 2400 N HYPERION AVE 90027

Application / Permit
19016-10000-33244
Plan Check / Job No.
B19LA22033
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
INTERIOR AND EXTERIOR ALTERATION OF (E) OFFICE SPACE. NEW ACCESSIBLE RESTROOMS AND NEW WINDOWS. UNDERPINNING (E) FOUNDATION, NEW PAD FOOTINGS AND MECHANICAL LIFT PER ENGINEER OF RECORD. (NO CHANGE OF USE)
Permit Issued
Issued on 10/8/2020
Issuing Office
Current Status
Permit Finaled on 10/26/2021

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/18/2019 CRISTINA SALAZAR
Corrections Issued 10/23/2019 CRISTINA SALAZAR
Applicant returned to address corrections 11/6/2019 CRISTINA SALAZAR
Applicant returned to address corrections 11/12/2019 CRISTINA SALAZAR
Applicant returned to address corrections 12/2/2019 CRISTINA SALAZAR
Applicant returned to address corrections 12/11/2019 CRISTINA SALAZAR
Plan Check Approved 2/13/2020 CRISTINA SALAZAR
Plan Check Approved 2/13/2020 AUNG SOE
Building Plans Picked Up 9/9/2020 APPLICANT
Issued 10/8/2020 APPLICANT
Permit Finaled 10/26/2021 SORIN CIRSTOIU

Permit Application Clearance Information

"Q" conditions Cleared 11/6/2019 JOSE ROMERO-NAVARRO
Grading Pre-Inspection Cleared 11/12/2019 DAVID FONSECA

Contact Information

Architect Neubert,, Aaron Douglas; Lic. No.: C29005 3052 BERKELEY CIRCLE      LOS ANGELES, CA 90026
Contractor City Constructors Inc; Lic. No.: 834591-B 450 S RAYMOND AVENUE      PASADENA, CA 91105
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/13/2020 Approved EDWIN GREGORYONA
Deputy Drilled-In Anchors 2/10/2021 Partial Approval EDWIN GREGORYONA
Footing/Foundation/Slab 2/26/2021 Approved RUSSELL BONVOULOIR
Wood Frame 2/26/2021 Conditional Approval RUSSELL BONVOULOIR
Deputy Wood Construction 4/1/2021 Conditional Approval RUSSELL BONVOULOIR
Wood Frame 4/7/2021 Approved EDWIN GREGORYONA
Drywall Nailing 5/3/2021 Approved DANIEL COLLINS
Pre-Inspection 6/4/2021 Approved RUSSELL BONVOULOIR
Final 10/6/2021 Not Ready for Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 10/6/2021 Not Ready for Inspection SORIN CIRSTOIU
Final 10/14/2021 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/14/2021 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 10/14/2021 Approved SORIN CIRSTOIU
Final 10/26/2021 Permit Finaled SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 10/26/2021 SGSOV Approved SORIN CIRSTOIU