2400 N HYPERION AVE 90027
Certificate Information: 2400 N HYPERION AVE 90027
- Application / Permit
- 19016-10000-33244
- Plan Check / Job No.
- B19LA22033
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR AND EXTERIOR ALTERATION OF (E) OFFICE SPACE. NEW ACCESSIBLE RESTROOMS AND NEW WINDOWS. UNDERPINNING (E) FOUNDATION, NEW PAD FOOTINGS AND MECHANICAL LIFT PER ENGINEER OF RECORD. (NO CHANGE OF USE)
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- Permit Finaled on 10/26/2021
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2019 | CRISTINA SALAZAR |
| Corrections Issued | 10/23/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 11/6/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 11/12/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/2/2019 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/11/2019 | CRISTINA SALAZAR |
| Plan Check Approved | 2/13/2020 | CRISTINA SALAZAR |
| Plan Check Approved | 2/13/2020 | AUNG SOE |
| Building Plans Picked Up | 9/9/2020 | APPLICANT |
| Issued | 10/8/2020 | APPLICANT |
| Permit Finaled | 10/26/2021 | SORIN CIRSTOIU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 11/6/2019 | JOSE ROMERO-NAVARRO |
| Grading Pre-Inspection | Cleared | 11/12/2019 | DAVID FONSECA |
Contact Information
| Architect | Neubert,, Aaron Douglas; Lic. No.: C29005 | 3052 BERKELEY CIRCLE LOS ANGELES, CA 90026 |
| Contractor | City Constructors Inc; Lic. No.: 834591-B | 450 S RAYMOND AVENUE PASADENA, CA 91105 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/13/2020 | Approved | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 2/10/2021 | Partial Approval | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 2/26/2021 | Approved | RUSSELL BONVOULOIR |
| Wood Frame | 2/26/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Deputy Wood Construction | 4/1/2021 | Conditional Approval | RUSSELL BONVOULOIR |
| Wood Frame | 4/7/2021 | Approved | EDWIN GREGORYONA |
| Drywall Nailing | 5/3/2021 | Approved | DANIEL COLLINS |
| Pre-Inspection | 6/4/2021 | Approved | RUSSELL BONVOULOIR |
| Final | 10/6/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 10/6/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 10/6/2021 | Not Ready for Inspection | SORIN CIRSTOIU |
| Final | 10/14/2021 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 10/14/2021 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 10/14/2021 | Approved | SORIN CIRSTOIU |
| Final | 10/26/2021 | Permit Finaled | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 10/26/2021 | SGSOV Approved | SORIN CIRSTOIU |