1262 E PALMETTO ST 1ST FLR 90013
Certificate Information: 1262 E PALMETTO ST 1ST FLR 90013
- Application / Permit
- 19016-10000-32786
- Plan Check / Job No.
- B19LA21761
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CHANGE OF USE ROM RETAIL TO OFFICE AND TENANT IMPROVEMENT.
- Permit Issued
- Issued on 3/17/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/18/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | JOHNNY WU |
| Disabled Access Plans Picked Up | 10/25/2019 | APPLICANT |
| Corrections Issued | 10/30/2019 | JOHNNY WU |
| Quality Review Completed | 11/7/2019 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 11/20/2019 | APPLICANT |
| Applicant returned to address corrections | 3/12/2020 | JOHNNY WU |
| Plan Check Approved | 3/12/2020 | JOHNNY WU |
| Issued | 3/17/2020 | LADBS |
| CofO in Progress | 10/5/2021 | DANIEL COLLINS |
| CofO Issued | 11/18/2021 | ERNESTO CORRAL |
| Permit Finaled | 11/18/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| ZA Case | Cleared | 12/24/2019 | JOE LUCKEY |
| ZA Case | Cleared | 12/24/2019 | JOE LUCKEY |
| ZI | Cleared | 12/24/2019 | JOE LUCKEY |
| DAS Clearance | Cleared | 1/24/2020 | JOHNNY WU |
| Project located in CRA area | Cleared | 1/24/2020 | GISELLE CORELLA |
| ZI | Cleared | 1/24/2020 | GISELLE CORELLA |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2020 | JUAN ASHTON |
| Green Code | Cleared | 2/5/2020 | VIVIAN LAO |
| Sewer availability | Cleared | 3/12/2020 | JEANIE LAM |
Contact Information
| Architect | Rios,, Mark William; Lic. No.: C15744 | 3101 W EXPOSITION PLACE LOS ANGELES, CA 90018 |
| Contractor | Taslimi Construction Co Inc; Lic. No.: 475159-B | 1805 COLORADO AVENUE SANTA MONICA, CA 90404 |
| Engineer | Mahjoub,, Nina Azadeh; Lic. No.: C78947 | 21400 BURBANK BLVD 114 WOODLAND HILLS, CA 91367 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/15/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 6/16/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 6/17/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 6/22/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 6/23/2020 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 6/24/2020 | Partial Approval | LANNY MERRICK |
| Deputy Methane Barrier | 7/1/2020 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Approved | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/6/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 7/7/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/8/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/9/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/10/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/10/2020 | Conditional Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 7/10/2020 | Partial Approval | LANNY MERRICK |
| METHANE-Rough | 7/10/2020 | Partial Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/13/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 7/13/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 7/14/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/14/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/15/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Methane Barrier | 7/15/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/15/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Drilled-In Anchors | 7/16/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Reinf. Concrete | 7/16/2020 | Conditional Approval | RONALD PACHECO |
| Deputy Drilled-In Anchors | 7/17/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/17/2020 | Conditional Approval | LANNY MERRICK |
| METHANE-Rough | 7/17/2020 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/20/2020 | Conditional Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 7/20/2020 | Partial Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/21/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/22/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/23/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Reinf. Concrete | 7/24/2020 | Conditional Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 7/28/2020 | Partial Approval | LANNY MERRICK |
| Excavation/Setback/Form/Re-Bar | 7/29/2020 | Partial Approval | LANNY MERRICK |
| Light Gage Steel Frame | 9/29/2020 | Approved | LANNY MERRICK |
| Drywall Nailing | 10/6/2020 | Approved | LANNY MERRICK |
| Drywall Nailing | 10/15/2020 | Not Ready for Inspection | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 10/20/2020 | Partial Approval | LANNY MERRICK |
| Deputy Steel/Welding | 10/27/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 10/28/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 10/29/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 10/30/2020 | Conditional Approval | LANNY MERRICK |
| Deputy Steel/Welding | 11/2/2020 | Conditional Approval | LANNY MERRICK |
| Light Gage Steel Frame | 12/1/2020 | Partial Approval | LANNY MERRICK |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Not Ready for Inspection | LANNY MERRICK |
| Drywall Nailing | 12/17/2020 | Partial Approval | LANNY MERRICK |
| Light Gage Steel Frame | 1/7/2021 | Partial Approval | LANNY MERRICK |
| Footing/Foundation/Slab | 1/28/2021 | Partial Approval | RONALD PACHECO |
| Footing/Foundation/Slab | 1/29/2021 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 2/12/2021 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 2/18/2021 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 3/4/2021 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 3/15/2021 | Partial Approval | MARK FERRARI |
| Light Gage Steel Frame | 4/6/2021 | Partial Approval | RONALD PACHECO |
| Wood Frame | 4/6/2021 | Partial Approval | RONALD PACHECO |
| Drywall Nailing | 4/14/2021 | Partial Approval | RONALD PACHECO |
| T-Bar Ceiling | 4/14/2021 | Partial Approval | RONALD PACHECO |
| Light Gage Steel Frame | 5/11/2021 | Approved | LANNY MERRICK |
| Final | 7/16/2021 | Partial Inspection | LANNY MERRICK |
| Green Building Final | 7/16/2021 | Approved | LANNY MERRICK |
| Green Building Rough | 7/16/2021 | Approved | LANNY MERRICK |
| METHANE-Final | 7/16/2021 | Approved | LANNY MERRICK |
| METHANE-Rough | 7/16/2021 | Approved | LANNY MERRICK |
| Reinforced Masonry Frame | 7/16/2021 | Approved | LANNY MERRICK |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | LANNY MERRICK |
| Smoke Detectors | 7/16/2021 | Approved | LANNY MERRICK |
| Pre-Inspection | 7/19/2021 | Partial Inspection | LANNY MERRICK |
| Final | 8/6/2021 | Not Ready for Inspection | LANNY MERRICK |
| Final | 8/23/2021 | Not Ready for Inspection | LANNY MERRICK |
| Pre-Inspection | 8/24/2021 | Partial Inspection | LANNY MERRICK |
| Final | 9/13/2021 | Conditional Approval | DANIEL COLLINS |
| Pre-Inspection | 10/26/2021 | Partial Inspection | DANIEL COLLINS |