2561 W AVENUE 30 90065

Certificate Information: 2561 W AVENUE 30 90065

Application / Permit
19016-10000-32723
Plan Check / Job No.
B19LA21712
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 1 (N) CANTILEVER COLUMN AND 2 (N) MOMENT FRAMES
Permit Issued
Issued on 4/13/2020
Issuing Office
Current Status
CofC Issued on 8/12/2021

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 11/6/2019 HANS SANTIAGO
Corrections Issued 11/12/2019 HANS SANTIAGO
Quality Review Completed 11/14/2019 SAI KHUM
Building Plans Picked Up 11/21/2019 APPLICANT
Applicant returned to address corrections 1/28/2020 HANS SANTIAGO
Plan Check Approved 2/6/2020 ANDREW SANTIAGO
Issued 4/13/2020 APPLICANT
OK for CofC 2/8/2021 MARK FERRARI
CofC Issued 8/12/2021 WINSTON DUNNING

Permit Application Clearance Information

ZI Cleared 12/23/2019 RICHARD REASER
Miscellaneous Cleared 2/6/2020 TERRI OSBORNE
Housing rent stabilization Cleared 3/5/2020 MICHAEL SOTO

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/17/2020 Not Ready for Inspection MARK FERRARI
Pre-Inspection 8/17/2020 Approved MARK FERRARI
Footing/Foundation/Slab 8/20/2020 Partial Approval MARK FERRARI
Wood Frame 8/20/2020 Partial Inspection MARK FERRARI
Deputy Drilled-In Anchors 9/10/2020 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 9/11/2020 Approved MARK FERRARI
Structural Steel Frame 9/11/2020 Partial Approval MARK FERRARI
Wood Frame 9/11/2020 Not Ready for Inspection MARK FERRARI
Deputy Reinf. Concrete 9/15/2020 Conditional Approval MARK FERRARI
Special/Order Compliance 9/29/2020 Corrections Issued MARK FERRARI
Structural Steel Frame 9/29/2020 Approved MARK FERRARI
Wood Frame 9/29/2020 Approved MARK FERRARI
Interior/Exterior Lathing 1/4/2021 Corrections Issued MARK FERRARI
Final 1/15/2021 Corrections Issued JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 1/15/2021 SGSOV Not Ready JONATHAN QUACH
Smoke Detectors 1/15/2021 Approved JONATHAN QUACH
Final 2/8/2021 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 2/8/2021 SGSOV Approved MARK FERRARI