2561 W AVENUE 30 90065
Certificate Information: 2561 W AVENUE 30 90065
- Application / Permit
- 19016-10000-32723
- Plan Check / Job No.
- B19LA21712
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 1 (N) CANTILEVER COLUMN AND 2 (N) MOMENT FRAMES
- Permit Issued
- Issued on 4/13/2020
- Issuing Office
- Current Status
- CofC Issued on 8/12/2021
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | HANS SANTIAGO |
| Corrections Issued | 11/12/2019 | HANS SANTIAGO |
| Quality Review Completed | 11/14/2019 | SAI KHUM |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Applicant returned to address corrections | 1/28/2020 | HANS SANTIAGO |
| Plan Check Approved | 2/6/2020 | ANDREW SANTIAGO |
| Issued | 4/13/2020 | APPLICANT |
| OK for CofC | 2/8/2021 | MARK FERRARI |
| CofC Issued | 8/12/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| ZI | Cleared | 12/23/2019 | RICHARD REASER |
| Miscellaneous | Cleared | 2/6/2020 | TERRI OSBORNE |
| Housing rent stabilization | Cleared | 3/5/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Courteous Construction Co Inc; Lic. No.: 567324-B | P O BOX 9287 GLENDALE, CA 91226 |
| Engineer | Rezazadeh,, Mehdi; Lic. No.: C49626 | P O BOX 98 DANVILLE, CA 94526 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/17/2020 | Not Ready for Inspection | MARK FERRARI |
| Pre-Inspection | 8/17/2020 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 8/20/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 8/20/2020 | Partial Inspection | MARK FERRARI |
| Deputy Drilled-In Anchors | 9/10/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 9/11/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 9/11/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 9/11/2020 | Not Ready for Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 9/15/2020 | Conditional Approval | MARK FERRARI |
| Special/Order Compliance | 9/29/2020 | Corrections Issued | MARK FERRARI |
| Structural Steel Frame | 9/29/2020 | Approved | MARK FERRARI |
| Wood Frame | 9/29/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 1/4/2021 | Corrections Issued | MARK FERRARI |
| Final | 1/15/2021 | Corrections Issued | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 1/15/2021 | Approved | JONATHAN QUACH |
| Final | 2/8/2021 | OK for CofC | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 2/8/2021 | SGSOV Approved | MARK FERRARI |