2249 N CHELAN PL 90046

Certificate Information: 2249 N CHELAN PL 90046

Application / Permit
19016-10000-32721
Plan Check / Job No.
B19LA21711
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF (E) 1-STORY SFD. ADD NEW WINDOWS/DOORS, REPAIR (E) ROOF, ADD BATHROOM. NO ADDED FLOOR AREA.
Permit Issued
Issued on 1/28/2020
Issuing Office
Valley
Current Status
Permit Finaled on 8/30/2023

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 SAMUEL GONZALEZ
Corrections Issued 10/31/2019 SAMUEL GONZALEZ
Quality Review Completed 11/7/2019 QUAN NGHIEM
Building Plans Picked Up 11/13/2019 APPLICANT
Plan Check Approved 12/18/2019 SAMUEL GONZALEZ
Issued 1/28/2020 LADBS
Permit Finaled 8/28/2023 BRIAN SULLIVAN

Permit Application Clearance Information

Specific Plan Cleared 12/10/2019 LIZZI BEDUYA
Grading Pre-Inspection Cleared 12/18/2019 SAMUEL GONZALEZ

Contact Information

Contractor Imbuia Construction Inc; Lic. No.: 796602-B 4751 DEL MORENO DR      WOODLAND HILLS, CA 91364
Engineer Fischer,, Kurt Mark; Lic. No.: S5432 PO BOX 809      POWAY, CA 92074

Inspector Information

ROY SPAULDING, (213) 202-3461 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/24/2020 Partial Approval BRIAN SULLIVAN
Pre-Inspection 2/24/2020 Corrections Issued BRIAN SULLIVAN
Special/Order Compliance 12/14/2020 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 3/24/2021 Partial Approval BRIAN SULLIVAN
Special/Order Compliance 3/24/2021 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2021 Approved BRIAN SULLIVAN
Wood Frame 12/2/2021 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 12/10/2021 Partial Approval BRIAN SULLIVAN
Wood Frame 12/10/2021 Approved BRIAN SULLIVAN
Insulation 1/10/2022 Approved BRIAN SULLIVAN
Drywall Nailing 1/27/2022 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 4/6/2022 Approved BRIAN SULLIVAN
Pre-Inspection 4/6/2022 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 4/14/2022 Approved BRIAN SULLIVAN
Final 8/15/2023 Not Ready for Inspection BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/15/2023 SGSOV Not Ready BRIAN SULLIVAN
Smoke Detectors 8/15/2023 Approved BRIAN SULLIVAN
Final 8/28/2023 Permit Finaled BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 8/28/2023 SGSOV Approved BRIAN SULLIVAN