1416 N MARTEL AVE 90046
Certificate Information: 1416 N MARTEL AVE 90046
- Application / Permit
- 19016-10000-32712
- Plan Check / Job No.
- B19LA21702
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAME.
- Permit Issued
- Issued on 4/13/2020
- Issuing Office
- Current Status
- CofC Issued on 7/2/2020
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | MANUEL MONTUFAR |
| Corrections Issued | 11/29/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/9/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/7/2020 | MANUEL MONTUFAR |
| Issued | 4/13/2020 | APPLICANT |
| OK for CofC | 6/30/2020 | FELIX CEBALLOS |
| CofC Issued | 7/2/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/16/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/24/2020 | Corrections Issued | FELIX CEBALLOS |
| Pre-Inspection | 4/27/2020 | Partial Inspection | FELIX CEBALLOS |
| Deputy Steel/Welding | 5/11/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Drilled-In Anchors | 5/12/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 5/13/2020 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 5/13/2020 | Approved | FELIX CEBALLOS |
| Structural Steel Frame | 5/13/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 5/13/2020 | Approved | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 5/15/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Wood Construction | 5/19/2020 | Conditional Approval | FRED WOHLFARTH |
| Structural Steel Frame | 5/20/2020 | Approved | MARK FERRARI |
| Wood Frame | 5/20/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 5/28/2020 | Approved | FELIX CEBALLOS |
| Final | 6/17/2020 | Not Ready for Inspection | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 6/17/2020 | SGSOV Not Ready | FELIX CEBALLOS |
| Smoke Detectors | 6/17/2020 | Approved | FELIX CEBALLOS |
| Final | 6/30/2020 | OK for CofC | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2020 | SGSOV Approved | FELIX CEBALLOS |