700 S MANHATTAN PL 1-160 90005
Certificate Information: 700 S MANHATTAN PL 1-160 90005
- Application / Permit
- 19016-10000-32690
- Plan Check / Job No.
- B19LA21687
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Day Care Facility adults
- Work Description
- CHANGE A PORTION OF USE ON GROUND LEVEL FROM RETAIL AND RESTURANT TO ELDERLY DAYCARE. INTERIOR TENANT IMPROVEMENT. REMOVE AND BUILD NEW INTERIOR PARTITIONS AND DOORS, ADD FIXTURES TO RESTROOMS, AND ADD NEW FLOOR, WALL, AND CEILING FINISHES. CHANGING OCCUPANCY FROM A2 AND M TO I-4.
- Permit Issued
- Issued on 4/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | ALBERT SERVIN |
| Corrections Issued | 11/5/2019 | ALBERT SERVIN |
| Quality Review Completed | 11/6/2019 | KEN GILL |
| Building Plans Picked Up | 11/12/2019 | APPLICANT |
| Disabled Access Plans Picked Up | 1/6/2020 | APPLICANT |
| Green Plans Picked Up | 1/6/2020 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | ALBERT SERVIN |
| Applicant returned to address corrections | 2/7/2020 | ALBERT SERVIN |
| Plan Check Approved | 3/6/2020 | ALBERT SERVIN |
| Issued | 4/14/2020 | LADBS |
| TCO Issued (Expire Date: 09-21-2021) | 3/25/2021 | ERNESTO CORRAL |
| CofO in Progress | 5/27/2021 | TERRY HERR |
| CofO Issued | 5/27/2021 | TERRY HERR |
| Permit Finaled | 5/27/2021 | TERRY HERR |
Permit Application Clearance Information
| Miscellaneous | Cleared | 11/14/2019 | JOE LUCKEY |
| Project located in CRA area | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| ZA Case | Cleared | 11/14/2019 | JOE LUCKEY |
| Green Code | Cleared | 1/31/2020 | VIVIAN LAO |
| Fire Marshall Fire Life Safety | Cleared | 2/4/2020 | OSCAR SALGADO JR |
| DAS Clearance | Cleared | 2/5/2020 | ALBERT SERVIN |
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2020 | JEANETTE VONG |
| Sewer availability | Cleared | 2/7/2020 | JEANETTE VONG |
| Comm Cor/Mini-Mall | Cleared | 3/2/2020 | ANACANY HURTADO |
Contact Information
| Architect | Pak,, Christopher C; Lic. No.: C25621 | 3530 WILSHIRE BLVD SUITE 615 LOS ANGELES, CA 90010 |
| Contractor | Philmont Management Inc; Lic. No.: 808686-B | 3450 WILSHIRE BLVD #850 LOS ANGELES, CA 90010 |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 8/21/2020 | Approved | TIMOTHY BUXTON |
| Pre-Inspection | 8/21/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 9/11/2020 | Approved | RAFAEL ESPINOZA |
| T-Bar Ceiling | 10/5/2020 | Approved | TIMOTHY BUXTON |
| Drywall Nailing | 10/9/2020 | Approved | TIMOTHY BUXTON |
| Green Building Rough | 10/23/2020 | Approved | KATY RAMIREZ |
| Pre-Inspection | 3/4/2021 | Approved | ERNESTO CORRAL |
| Final | 3/5/2021 | Corrections Issued | ERNESTO CORRAL |
| Green Building Final | 3/5/2021 | Approved | ERNESTO CORRAL |
| METHANE-Final | 3/5/2021 | Approved | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 3/5/2021 | SGSOV Approved | ERNESTO CORRAL |
| Smoke Detectors | 3/5/2021 | Approved | ERNESTO CORRAL |
| Final | 5/27/2021 | OK to Issue CofO | TERRY HERR |