2526 S CENTINELA AVE 90064
Certificate Information: 2526 S CENTINELA AVE 90064
- Application / Permit
- 19016-10000-32651
- Plan Check / Job No.
- B19LA21658
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CHAPTER 93 INSTALL (2) STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 12/2/2022
- Issuing Office
- Metro
- Current Status
- CofC Issued on 7/14/2023
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | HANS SANTIAGO |
| Corrections Issued | 11/12/2019 | HANS SANTIAGO |
| Quality Review Completed | 11/14/2019 | SAI KHUM |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Plan Check Approved | 1/7/2020 | ANDREW SANTIAGO |
| Issued | 12/2/2022 | APPLICANT |
| OK for CofC | 7/10/2023 | MICHAEL PETRUSKO |
| CofC Issued | 7/14/2023 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/1/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 19528 VENTURA BLVD #300 TARZANA, CA 91356 |
| Engineer | Tajvidi,, Seyed Mohammad; Lic. No.: C84559 | 9163 LEROY STREET SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/22/2022 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 1/25/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 1/25/2023 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 1/26/2023 | Approved | ALAN NOVAK |
| Structural Steel Frame | 1/26/2023 | Not Ready for Inspection | ALAN NOVAK |
| Wood Frame | 1/26/2023 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 1/30/2023 | Conditional Approval | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 2/7/2023 | Approved | FARHAD DADBIN |
| Final | 5/24/2023 | Conditional Approval | MICHAEL PETRUSKO |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Approved | MICHAEL PETRUSKO |
| Smoke Detectors | 5/24/2023 | Approved | MICHAEL PETRUSKO |
| Final | 7/10/2023 | OK for CofC | MICHAEL PETRUSKO |