1122 S CARDIFF AVE 90035
Certificate Information: 1122 S CARDIFF AVE 90035
- Application / Permit
- 19016-10000-32648
- Plan Check / Job No.
- B19LA21650
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ePLAN 1176 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new steel ordinary moment frame and wood shear wall
- Permit Issued
- Issued on 5/5/2020
- Issuing Office
- Current Status
- CofC Issued on 10/2/2020
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2019 | THOMAS SHERMAN |
| Corrections Issued | 12/23/2019 | THOMAS SHERMAN |
| Quality Review Completed | 12/25/2019 | HANS SANTIAGO |
| Plan Check Approved | 2/14/2020 | THOMAS SHERMAN |
| Issued | 5/5/2020 | APPLICANT |
| OK for CofC | 9/22/2020 | GRANT WOODS |
| CofC Issued | 10/2/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/17/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Interserve Construction Corp; Lic. No.: 968925-B | 7524 MELROSE AVE LOS ANGELES, CA 90046 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/5/2020 | No Access for Inspection | DARRYL ARNOLD |
| METHANE-Final | 8/5/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/5/2020 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/5/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/26/2020 | Approved | GRANT WOODS |
| Structural Steel Frame | 8/26/2020 | Partial Approval | GRANT WOODS |
| Wood Frame | 8/26/2020 | Partial Approval | GRANT WOODS |
| Structural Steel Frame | 9/2/2020 | Approved | GRANT WOODS |
| Wood Frame | 9/2/2020 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 9/4/2020 | Not Ready for Inspection | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Approved | GRANT WOODS |
| Masonry Wall/Backfill | 9/4/2020 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 9/4/2020 | Partial Inspection | GRANT WOODS |
| Wood Frame | 9/4/2020 | Approved | GRANT WOODS |
| Deputy Wood Construction | 9/8/2020 | Conditional Approval | GRANT WOODS |
| Interior/Exterior Lathing | 9/14/2020 | Approved | GRANT WOODS |
| Final | 9/22/2020 | OK for CofC | GRANT WOODS |
| METHANE-Final | 9/22/2020 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/22/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 9/22/2020 | Approved | GRANT WOODS |