688 N BIENVENEDA AVE 90272
Certificate Information: 688 N BIENVENEDA AVE 90272
- Application / Permit
- 19016-10000-32647
- Plan Check / Job No.
- B19LA21647
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEAR WALL.
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofC Issued on 7/7/2022
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/20/2019 | MANUEL MONTUFAR |
| Corrections Issued | 11/28/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/2/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 5/6/2020 | MANUEL MONTUFAR |
| Plan Check Approved | 6/19/2020 | MANUEL MONTUFAR |
| Issued | 4/13/2022 | APPLICANT |
| OK for CofC | 7/1/2022 | SORIN CIRSTOIU |
| CofC Issued | 7/7/2022 | DAVID TSAU |
Permit Application Clearance Information
| Historic monument | Cleared | 12/10/2019 | MELISSA JONES |
| ZI | Cleared | 12/10/2019 | ANNA VAN |
| Housing rent stabilization | Cleared | 1/27/2022 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Arc Alliance Retrofitting And Construction Incorporated; Lic. No.: 1030899-B | 15521 MARILLA STREET NORTH HILLS, CA 91343 |
| Engineer | Watson,, Darren S; Lic. No.: C87717 | 3704 MIDVALE AVE 6 LOS ANGELES, CA 90034 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/16/2022 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 5/24/2022 | Conditional Approval | JOHN DODGE |
| Wall Anchors | 5/25/2022 | Partial Approval | GRANT WOODS |
| Wood Frame | 5/25/2022 | Partial Approval | GRANT WOODS |
| Deputy Wood Construction | 5/27/2022 | Approved | GRANT WOODS |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2022 | Approved | GRANT WOODS |
| Structural Steel Frame | 6/3/2022 | Approved | GRANT WOODS |
| Final | 6/15/2022 | No Access for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2022 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 6/15/2022 | No Access for Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 6/22/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Final | 6/28/2022 | Partial Inspection | SORIN CIRSTOIU |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Not Ready | SORIN CIRSTOIU |
| Smoke Detectors | 6/28/2022 | Partial Inspection | SORIN CIRSTOIU |
| Final | 6/30/2022 | Not Ready for Inspection | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 6/30/2022 | Approved | DERRICK SPENCER |
| Final | 7/1/2022 | OK for CofC | SORIN CIRSTOIU |