688 N BIENVENEDA AVE 90272

Certificate Information: 688 N BIENVENEDA AVE 90272

Application / Permit
19016-10000-32647
Plan Check / Job No.
B19LA21647
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL PLYWOOD SHEAR WALL.
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofC Issued on 7/7/2022

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 11/20/2019 MANUEL MONTUFAR
Corrections Issued 11/28/2019 MANUEL MONTUFAR
Quality Review Completed 12/2/2019 HANS SANTIAGO
Applicant returned to address corrections 5/6/2020 MANUEL MONTUFAR
Plan Check Approved 6/19/2020 MANUEL MONTUFAR
Issued 4/13/2022 APPLICANT
OK for CofC 7/1/2022 SORIN CIRSTOIU
CofC Issued 7/7/2022 DAVID TSAU

Permit Application Clearance Information

Historic monument Cleared 12/10/2019 MELISSA JONES
ZI Cleared 12/10/2019 ANNA VAN
Housing rent stabilization Cleared 1/27/2022 PHILLIP MUNGUIA

Contact Information

Contractor Arc Alliance Retrofitting And Construction Incorporated; Lic. No.: 1030899-B 15521 MARILLA STREET      NORTH HILLS, CA 91343
Engineer Watson,, Darren S; Lic. No.: C87717 3704 MIDVALE AVE 6      LOS ANGELES, CA 90034

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/16/2022 Approved GRANT WOODS
Deputy Drilled-In Anchors 5/24/2022 Conditional Approval JOHN DODGE
Wall Anchors 5/25/2022 Partial Approval GRANT WOODS
Wood Frame 5/25/2022 Partial Approval GRANT WOODS
Deputy Wood Construction 5/27/2022 Approved GRANT WOODS
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Approved GRANT WOODS
Structural Steel Frame 6/3/2022 Approved GRANT WOODS
Final 6/15/2022 No Access for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 6/15/2022 SGSOV Not Ready GRANT WOODS
Smoke Detectors 6/15/2022 No Access for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Not Ready SORIN CIRSTOIU
Final 6/28/2022 Partial Inspection SORIN CIRSTOIU
SGSOV-Seismic Gas S/O Valve 6/28/2022 SGSOV Not Ready SORIN CIRSTOIU
Smoke Detectors 6/28/2022 Partial Inspection SORIN CIRSTOIU
Final 6/30/2022 Not Ready for Inspection DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved DERRICK SPENCER
Smoke Detectors 6/30/2022 Approved DERRICK SPENCER
Final 7/1/2022 OK for CofC SORIN CIRSTOIU