19755 W VANOWEN ST 91306

Certificate Information: 19755 W VANOWEN ST 91306

Application / Permit
19016-10000-32617
Plan Check / Job No.
B19LA21625
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
INTERIOR TENANT IMPROVEMENT. CHANGE OF USE FROM RETAIL TO RESTAURANT. CONSTRUCTION OF NEW NON-BEARING WALLS FOR CONFIGURATION OF KITCHEN AND CUSTOMER AREAS.
Permit Issued
Issued on 1/17/2020
Issuing Office
Metro
Current Status
CofO Issued on 6/3/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 GEORGE ALVAREZ
Corrections Issued 10/29/2019 GEORGE ALVAREZ
Quality Review Completed 11/2/2019 STANLEY RAAP
Building Plans Picked Up 11/13/2019 APPLICANT
Disabled Access Plans Picked Up 11/14/2019 APPLICANT
Plan Check Approved 12/26/2019 GEORGE ALVAREZ
Issued 1/17/2020 LADBS
CofO in Progress 5/5/2020 JEFFREY FULTON
Permit Finaled 6/3/2020 JEFFREY DURAN
CofO Issued 6/3/2020 JEFFREY DURAN
Permit Finaled 6/3/2020 JEFFREY DURAN

Permit Application Clearance Information

"Q" conditions Cleared 11/14/2019 RICHARD REASER
CPC Cleared 11/14/2019 RICHARD REASER
Miscellaneous Cleared 11/14/2019 RICHARD REASER
ZA Case Cleared 11/14/2019 RICHARD REASER
DAS Clearance Cleared 12/5/2019 GEORGE ALVAREZ
Food Service Establishment Cleared 12/16/2019 KENNETH BROWNE
Eng Process Fee Ord 176,300 Cleared 12/20/2019 THOMAS LANG
Sewer availability Cleared 12/20/2019 THOMAS LANG
Food establishment approval Cleared 12/26/2019 LACDHS APPROVED

Contact Information

Architect Wang,, Gary H; Lic. No.: C32569 1000 CORPORATE CENTER DR SUITE 550      MONTEREY PARK, CA 91754
Contractor Koh'S Construction Co Inc; Lic. No.: 634540-B 1162 4TH AVE #4      LOS ANGELES, CA 90019

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/19/2020 Conditional Approval GARY EWELL
Light Gage Steel Frame 2/24/2020 Approved GARY EWELL
Drywall Nailing 2/26/2020 Approved GARY EWELL
T-Bar Ceiling 3/20/2020 Partial Inspection JEFFREY FULTON
Drywall Nailing 4/2/2020 Approved JONATHAN QUACH
Final 4/14/2020 Not Ready for Inspection JEFFREY FULTON
SGSOV-Seismic Gas S/O Valve 4/14/2020 SGSOV No Gas JEFFREY FULTON
Smoke Detectors 4/14/2020 Approved JEFFREY FULTON
Final 5/5/2020 OK to Issue CofO JEFFREY FULTON