4509 N VAN NOORD AVE 91604
Certificate Information: 4509 N VAN NOORD AVE 91604
- Application / Permit
- 19016-10000-32371
- Plan Check / Job No.
- B19LA21465
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Converision of (E) detached garage to an Accessory Dwelling Unit per AB 494 and SB 229. (N) roof framing.
- Permit Issued
- Issued on 10/17/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2019 | MONICA RAMIREZ |
| Corrections Issued | 10/9/2019 | MONICA RAMIREZ |
| Applicant returned to address corrections | 10/10/2019 | HELEN NGUYEN |
| Plan Check Approved | 10/11/2019 | ARSALAN SHABESTARI |
| Issued | 10/17/2019 | LADBS |
| CofO in Progress | 3/2/2020 | ARAM AVEDISIAN |
| CofO Issued | 3/21/2020 | MICHAEL SMITH |
| Permit Finaled | 3/21/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2019 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 10/9/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 10/11/2019 | JEANIE LAM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/31/2019 | Partial Approval | RAYMOND KEHOE |
| Deputy Drilled-In Anchors | 11/6/2019 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 11/12/2019 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 11/27/2019 | Approved | RAYMOND KEHOE |
| Deputy Drilled-In Anchors | 12/5/2019 | Approved | RAYMOND KEHOE |
| Footing/Foundation/Slab | 12/9/2019 | Approved | RAYMOND KEHOE |
| ELECTRICAL-Rough | 12/18/2019 | Approved | RAYMOND KEHOE |
| PLUMBING-Rough | 12/23/2019 | Approved | RAYMOND KEHOE |
| BUILDING-Rough-Frame | 12/27/2019 | Approved | RAYMOND KEHOE |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2019 | Partial Approval | RAYMOND KEHOE |
| Green Building Rough | 12/27/2019 | Approved | RAYMOND KEHOE |
| Insulation | 1/9/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 1/9/2020 | Partial Approval | RAYMOND KEHOE |
| Drywall Nailing | 1/16/2020 | Approved | RAYMOND KEHOE |
| Shower Pan | 1/16/2020 | Approved | RAYMOND KEHOE |
| Interior/Exterior Lathing | 1/23/2020 | Partial Approval | RAYMOND KEHOE |
| Final | 2/21/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Green Building Final | 2/21/2020 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/21/2020 | SGSOV Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 2/21/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/28/2020 | Approved | ARAM AVEDISIAN |
| Final | 2/28/2020 | OK to Issue CofO | ARAM AVEDISIAN |
| HVAC-Final | 2/28/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/28/2020 | Approved | ARAM AVEDISIAN |