822 W 10TH ST 90731
Certificate Information: 822 W 10TH ST 90731
- Application / Permit
- 19016-10000-32259
- Plan Check / Job No.
- B19LA21390
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. ISNTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 1/12/2022
- Issuing Office
- Current Status
- CofC Issued on 5/10/2022
Permit Application Status History
| Submitted | 12/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/2/2020 | MANUEL MONTUFAR |
| Corrections Issued | 1/7/2020 | MANUEL MONTUFAR |
| Quality Review Completed | 1/10/2020 | HANS SANTIAGO |
| Plan Check Approved | 4/10/2020 | MANUEL MONTUFAR |
| Issued | 1/12/2022 | APPLICANT |
| OK for CofC | 5/3/2022 | JOEY BUCHANAN |
| CofC Issued | 5/10/2022 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 12/21/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Vuoso And Sons Construction Inc; Lic. No.: 745803-B | PO BOX 6722 SAN PEDRO, CA 90734 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1730 E HOLLY AVE STE 107 EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/18/2022 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 3/3/2022 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 3/3/2022 | Approved | JOEY BUCHANAN |
| Structural Steel Frame | 3/3/2022 | Approved | JOEY BUCHANAN |
| Wood Frame | 3/3/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 3/8/2022 | Not Ready for Inspection | JOEY BUCHANAN |
| Wood Frame | 3/8/2022 | Approved | JOEY BUCHANAN |
| Interior/Exterior Lathing | 3/10/2022 | Approved | JOEY BUCHANAN |
| Final | 5/3/2022 | OK for CofC | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2022 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 5/3/2022 | Approved | JOEY BUCHANAN |