3800 S VERMONT AVE 90037
Certificate Information: 3800 S VERMONT AVE 90037
- Application / Permit
- 19016-10000-32148
- Plan Check / Job No.
- B19LA21342
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (4) Museum non-profit
- Work Description
- ePlan deferred item. Supplmental to 17010-10000-01465 for interior back-of-house metal stud framing for partitons and ceilings on levels 1-5.
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- Permit Finaled on 8/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/23/2019 | MINYE PAK |
| Plans on Hold | 10/23/2019 | MINYE PAK |
| Hold Released | 10/30/2019 | MINYE PAK |
| Corrections Issued | 10/31/2019 | TU HUA |
| Quality Review Completed | 10/31/2019 | MINYE PAK |
| Applicant returned to address corrections | 9/3/2020 | TU HUA |
| Plan Check Approved | 9/4/2020 | TU HUA |
| Issued | 9/4/2020 | APPLICANT |
| Permit Finaled | 8/24/2023 | JAMES POWERS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Hathaway Dinwiddie Construction Company; Lic. No.: 729664-B | 275 BATTERY STREET SUITE 300 SAN FRANCISCO, CA 941113330 |
| Engineer | Islam,, Mohammed Saiful; Lic. No.: S4083 | 155 N LAKE AVE SUITE 600 PASADENA, CA 91101 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 11/6/2020 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 11/6/2020 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/28/2020 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 12/28/2020 | Partial Approval | JAMES POWERS |
| Insulation | 1/26/2021 | No Access for Inspection | JAMES POWERS |
| Light Gage Steel Frame | 1/26/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 2/2/2021 | Partial Approval | JAMES POWERS |
| Insulation | 2/12/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 2/12/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 3/8/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 4/12/2021 | Partial Approval | JAMES POWERS |
| Insulation | 5/21/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 5/27/2021 | Partial Approval | JAMES POWERS |
| Insulation | 6/15/2021 | Partial Approval | JAMES POWERS |
| Insulation | 6/22/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/15/2021 | Partial Approval | JAMES POWERS |
| Insulation | 7/15/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 7/15/2021 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 8/4/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 8/4/2021 | Partial Approval | JAMES POWERS |
| Wall Anchors | 8/4/2021 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 8/11/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/18/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 9/2/2021 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 9/2/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/18/2021 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 11/9/2021 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/18/2021 | Partial Approval | TED RIES |
| Light Gage Steel Frame | 11/18/2021 | Partial Approval | TED RIES |
| Light Gage Steel Frame | 12/2/2021 | Partial Approval | TED RIES |
| Light Gage Steel Frame | 1/13/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 1/26/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 1/26/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 1/27/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 1/27/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 2/2/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 2/3/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 2/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 2/11/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 2/17/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 3/9/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 3/9/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 3/17/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 3/17/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 3/23/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 3/30/2022 | Partial Inspection | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/6/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 4/6/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Light Gage Steel Frame | 4/6/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Insulation | 4/18/2022 | Partial Approval | RUSSELL BONVOULOIR |
| Drywall Nailing | 4/26/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 4/26/2022 | Partial Approval | JAMES POWERS |
| Insulation | 5/4/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 5/4/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 5/9/2022 | Partial Approval | JAMES POWERS |
| Insulation | 5/9/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 5/9/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 5/23/2022 | Partial Approval | JAMES POWERS |
| Insulation | 5/23/2022 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 5/23/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 5/23/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 6/6/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 6/17/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 6/17/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 6/24/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/8/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/11/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 8/11/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 8/22/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 8/22/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 8/25/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 9/12/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 9/16/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/6/2022 | Partial Approval | JAMES POWERS |
| Insulation | 10/18/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 10/18/2022 | Partial Approval | JAMES POWERS |
| Insulation | 10/19/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 10/19/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 10/25/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/31/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 10/31/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 11/1/2022 | Partial Inspection | GREGORY POMISH |
| Drywall Nailing | 11/21/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 11/28/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 12/14/2022 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 12/14/2022 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 1/3/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 1/3/2023 | Not Ready for Inspection | JAMES POWERS |
| Light Gage Steel Frame | 1/5/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 1/23/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 2/17/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 3/21/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 3/23/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 4/4/2023 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 4/4/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 4/11/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 4/20/2023 | Partial Approval | GREGORY POMISH |
| Light Gage Steel Frame | 4/20/2023 | Partial Approval | GREGORY POMISH |
| Drywall Nailing | 5/11/2023 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 6/12/2023 | Partial Approval | LARRY ARNICK |
| Drywall Nailing | 7/3/2023 | Partial Approval | JAMES POWERS |
| T-Bar Ceiling | 7/3/2023 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 7/11/2023 | Partial Approval | JAMES POWERS |