1039 S SERRANO AVE 90006
Certificate Information: 1039 S SERRANO AVE 90006
- Application / Permit
- 19016-10000-32074
- Plan Check / Job No.
- B19LA21293
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFTT AS PER LABC CH. 93. INSTALL (3) STEEL CANTILEVER COLUMNS
- Permit Issued
- Issued on 12/8/2020
- Issuing Office
- Current Status
- CofC Issued on 5/5/2021
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | HANS SANTIAGO |
| Corrections Issued | 11/12/2019 | HANS SANTIAGO |
| Quality Review Completed | 11/14/2019 | SAI KHUM |
| Building Plans Picked Up | 12/9/2019 | APPLICANT |
| Plan Check Approved | 8/5/2020 | ANDREW SANTIAGO |
| Issued | 12/8/2020 | APPLICANT |
| OK for CofC | 5/4/2021 | DARRYL ARNOLD |
| CofC Issued | 5/5/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 7/30/2020 | MICAELA TORRES-GIL |
| Housing rent stabilization | Cleared | 12/2/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 1626 S MAYFLOWER AVE UNIT B MONROVIA, CA 91016 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/28/2020 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/30/2020 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/4/2021 | Approved | DARRYL ARNOLD |
| Wood Frame | 1/4/2021 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 1/5/2021 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 3/31/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/31/2021 | Approved | DARRYL ARNOLD |
| Final | 4/29/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/29/2021 | Corrections Issued | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 4/29/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 5/4/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 5/4/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/4/2021 | Approved | DARRYL ARNOLD |