2158 N MARIANNA AVE 90032

Certificate Information: 2158 N MARIANNA AVE 90032

Application / Permit
19016-10000-31960
Plan Check / Job No.
B19LA21229
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER ALBC CH 93. INSTALL (1) SCCS & (1) SHEAR WALL & (1) OMF.
Permit Issued
Issued on 2/24/2020
Issuing Office
Metro
Current Status
CofC Issued on 5/3/2021

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 GARO TELMI
Corrections Issued 11/18/2019 GARO TELMI
Quality Review Completed 11/22/2019 SAI KHUM
Building Plans Picked Up 11/26/2019 APPLICANT
Applicant returned to address corrections 1/10/2020 GARO TELMI
Plan Check Approved 2/4/2020 GARO TELMI
Issued 2/24/2020 LADBS
OK for CofC 4/19/2021 FRED WOHLFARTH
CofC Issued 5/3/2021 ERNESTO CORRAL

Permit Application Clearance Information

Historic Resource Verification Cleared 2/24/2020 GISELLE CORELLA
Housing rent stabilization Cleared 2/24/2020 MICHAEL GREGERSON
Redevelopment Project Area Cleared 2/24/2020 GISELLE CORELLA

Contact Information

Contractor Owner-Builder       ,
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/25/2020 Partial Approval MARK FERRARI
Footing/Foundation/Slab 7/14/2020 No Access for Inspection MARK FERRARI
Pre-Inspection 7/22/2020 Partial Inspection MARK FERRARI
Deputy Steel/Welding 8/11/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 8/13/2020 Conditional Approval MARK FERRARI
Deputy Steel/Welding 8/25/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 8/28/2020 Approved MARK FERRARI
Wood Frame 8/28/2020 Partial Approval MARK FERRARI
Deputy Reinf. Concrete 9/3/2020 Conditional Approval DARRYL ARNOLD
Insulation 10/14/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 10/16/2020 Approved MARK FERRARI
Wood Frame 10/16/2020 Approved MARK FERRARI
Interior/Exterior Lathing 11/5/2020 Corrections Issued MARK FERRARI
Final 1/22/2021 Corrections Issued MARK FERRARI
SGSOV-Seismic Gas S/O Valve 1/22/2021 SGSOV Not Ready MARK FERRARI
Smoke Detectors 1/22/2021 Approved MARK FERRARI
Final 4/19/2021 OK for CofC FRED WOHLFARTH
SGSOV-Seismic Gas S/O Valve 4/19/2021 SGSOV Approved FRED WOHLFARTH