5446 W ROMAINE ST 1-8 90038
Certificate Information: 5446 W ROMAINE ST 1-8 90038
- Application / Permit
- 19016-10000-31908
- Plan Check / Job No.
- B19LA21201
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (1) MOMENT FRAME AND 3 SCCS.
- Permit Issued
- Issued on 5/12/2023
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 2/14/2024
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | VARAND SARKISIAN |
| Corrections Issued | 11/18/2019 | VARAND SARKISIAN |
| Quality Review Completed | 11/21/2019 | SAI KHUM |
| Building Plans Picked Up | 12/19/2019 | APPLICANT |
| Plan Check Approved | 4/14/2020 | VARAND SARKISIAN |
| Issued | 5/12/2023 | APPLICANT |
| Permit Finaled | 2/14/2024 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 5/10/2023 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Farmand,, Anthony E; Lic. No.: C62595 | 2372 MORSE AVE STE 137 IRVINE, CA 92614 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/2/2023 | Conditional Approval | VAHE KELEDJIAN |
| Deputy Steel/Welding | 10/10/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/20/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/26/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 10/26/2023 | Partial Approval | JACOB MYERS |
| Deputy Reinf. Concrete | 10/26/2023 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 10/31/2023 | Conditional Approval | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2023 | Partial Approval | JACOB MYERS |
| Deputy Drilled-In Anchors | 11/3/2023 | Approved | JACOB MYERS |
| Deputy Reinf. Concrete | 11/3/2023 | Approved | JACOB MYERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/7/2023 | Approved | JACOB MYERS |
| Footing/Foundation/Slab | 11/7/2023 | Approved | JACOB MYERS |
| Structural Steel Frame | 11/7/2023 | Approved | JACOB MYERS |
| Wood Frame | 11/7/2023 | Approved | JACOB MYERS |
| Deputy Reinf. Concrete | 11/8/2023 | Approved | JACOB MYERS |
| Interior/Exterior Lathing | 11/20/2023 | Partial Inspection | JACOB MYERS |
| Final | 1/17/2024 | Partial Approval | JACOB MYERS |
| SGSOV-Seismic Gas S/O Valve | 1/17/2024 | SGSOV Approved | JACOB MYERS |
| Smoke Detectors | 1/17/2024 | Approved | JACOB MYERS |
| Final | 2/14/2024 | Permit Finaled | WINSTON DUNNING |