1513 N LINDACREST DR 90210
Certificate Information: 1513 N LINDACREST DR 90210
- Application / Permit
- 19016-10000-31806
- Plan Check / Job No.
- B19LA21135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERSION OF (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER ORDINANCE W/ NEW ATTACHED 5'-4" X 14'-7" TRELLIS.
- Permit Issued
- Issued on 5/22/2020
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 10/16/2019 | FARSHAD ALIMOHAMADI |
| Green Plans Picked Up | 10/22/2019 | APPLICANT |
| Quality Review Completed | 10/26/2019 | YOUNG KIM |
| Applicant returned to address corrections | 5/5/2020 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/20/2020 | FARSHAD ALIMOHAMADI |
| Issued | 5/22/2020 | APPLICANT |
| Building Plans Picked Up | 5/26/2020 | APPLICANT |
| CofO in Progress | 4/22/2026 | BRIAN SULLIVAN |
| Permit Finaled | 4/23/2026 | DEROLD HAUFF |
| CofO Issued | 4/23/2026 | DEROLD HAUFF |
| Permit Finaled | 4/23/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2020 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 5/1/2020 | DINAH GARIN |
| Sewer availability | Cleared | 5/1/2020 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 5/4/2020 | DINAH GARIN |
| Green Code | Cleared | 5/18/2020 | VIVIAN LAO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: C87383 | 1561 RUGBY CIR THOUSAND OAKS, CA 91360 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 8/4/2020 | Partial Approval | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 9/10/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 9/10/2020 | Approved | RAUL BARAJAS |
| Underground Mechanical | 9/10/2020 | Approved | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2020 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 12/24/2020 | Approved | RAUL BARAJAS |
| Green Building Rough | 12/24/2020 | Approved | RAUL BARAJAS |
| Insulation | 1/8/2021 | Approved | RAUL BARAJAS |
| Drywall Nailing | 1/14/2021 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/9/2021 | Approved | RAUL BARAJAS |
| Final | 11/15/2021 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/15/2021 | Approved | RAUL BARAJAS |
| Green Building Final | 11/15/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 11/15/2021 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 11/15/2021 | Approved | RAUL BARAJAS |
| Final | 11/23/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 11/30/2021 | Not Ready for Inspection | JUSTIN HAWLEY |
| Final | 12/13/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 1/12/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 4/22/2026 | OK to Issue CofO | BRIAN SULLIVAN |