6307 E ELGIN ST 90042

Certificate Information: 6307 E ELGIN ST 90042

Application / Permit
19016-10000-31739
Plan Check / Job No.
B19LA21091
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH. 93. INSTAL L (1) OMF AND (2) SCCS.
Permit Issued
Issued on 2/21/2020
Issuing Office
Metro
Current Status
CofC Issued on 9/17/2020

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 DANIEL SANJUAN
Corrections Issued 11/7/2019 DANIEL SANJUAN
Quality Review Completed 11/13/2019 SAI KHUM
Building Plans Picked Up 11/21/2019 APPLICANT
Plan Check Approved 1/17/2020 DANIEL SANJUAN
Issued 2/21/2020 LADBS
OK for CofC 9/11/2020 MARK FERRARI
CofC Issued 9/17/2020 ERNESTO CORRAL

Permit Application Clearance Information

HPOZ Cleared 12/23/2019 RICHARD REASER
Housing rent stabilization Cleared 2/20/2020 PHILLIP MUNGUIA

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2020 Corrections Issued MARK FERRARI
Wood Frame 6/4/2020 Partial Approval MARK FERRARI
Deputy Steel/Welding 6/26/2020 Partial Approval DARRYL ARNOLD
Deputy Steel/Welding 7/9/2020 Conditional Approval MARK FERRARI
Deputy Drilled-In Anchors 7/20/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 7/21/2020 Approved MARK FERRARI
Structural Steel Frame 7/21/2020 Corrections Issued MARK FERRARI
Wood Frame 8/6/2020 Approved MARK FERRARI
Interior/Exterior Lathing 8/12/2020 Approved MARK FERRARI
Final 8/26/2020 Conditional Approval MARK FERRARI
SGSOV-Seismic Gas S/O Valve 8/26/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 8/26/2020 Approved MARK FERRARI
Final 9/11/2020 OK for CofC MARK FERRARI