830 W BARTLETT ST 90012

Certificate Information: 830 W BARTLETT ST 90012

Application / Permit
19016-10000-31737
Plan Check / Job No.
B19LA21086
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
Permit Issued
Issued on 1/23/2020
Issuing Office
Metro
Current Status
CofC Issued on 5/26/2020

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Assigned to Plan Check Engineer 10/30/2019 ERWIN PASCUA
Corrections Issued 11/5/2019 ERWIN PASCUA
Quality Review Completed 11/6/2019 SAI KHUM
Building Plans Picked Up 11/8/2019 APPLICANT
Plan Check Approved 1/7/2020 ERWIN PASCUA
Issued 1/23/2020 LADBS
OK for CofC 5/18/2020 MARK FERRARI
CofC Issued 5/26/2020 DAVID TSAU

Permit Application Clearance Information

Project located in CRA area Cleared 12/5/2019 GRACIELA ACOSTA
ZI Cleared 12/5/2019 GRACIELA ACOSTA
Housing rent stabilization Cleared 1/15/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Courteous Construction Co Inc; Lic. No.: 567324-B P O BOX 9287      GLENDALE, CA 91226
Engineer Rezazadeh,, Mehdi; Lic. No.: C49626 P O BOX 98      DANVILLE, CA 94526

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2020 Approved MARK FERRARI
Deputy Reinf. Concrete 2/5/2020 Conditional Approval MARK FERRARI
Excavation/Setback/Form/Re-Bar 2/6/2020 Approved MARK FERRARI
Footing/Foundation/Slab 2/6/2020 Approved MARK FERRARI
Structural Steel Frame 2/6/2020 Partial Approval MARK FERRARI
Wood Frame 2/6/2020 Not Ready for Inspection MARK FERRARI
Deputy Reinf. Concrete 2/7/2020 Corrections Issued MARK FERRARI
Wood Frame 2/11/2020 Approved MARK FERRARI
Interior/Exterior Lathing 2/18/2020 Not Ready for Inspection MARK FERRARI
Special/Order Compliance 2/18/2020 Approved LANNY MERRICK
Interior/Exterior Lathing 3/31/2020 Approved DARRYL ARNOLD
Final 4/8/2020 Not Ready for Inspection DARRYL ARNOLD
METHANE-Final 4/8/2020 Partial Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/8/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/8/2020 Partial Approval DARRYL ARNOLD
Final 4/23/2020 Conditional Approval FELIX CEBALLOS
METHANE-Final 4/23/2020 Approved FELIX CEBALLOS
Smoke Detectors 4/23/2020 Approved FELIX CEBALLOS
Final 5/18/2020 OK for CofC MARK FERRARI