830 W BARTLETT ST 90012
Certificate Information: 830 W BARTLETT ST 90012
- Application / Permit
- 19016-10000-31737
- Plan Check / Job No.
- B19LA21086
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 5/26/2020
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2019 | ERWIN PASCUA |
| Corrections Issued | 11/5/2019 | ERWIN PASCUA |
| Quality Review Completed | 11/6/2019 | SAI KHUM |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Plan Check Approved | 1/7/2020 | ERWIN PASCUA |
| Issued | 1/23/2020 | LADBS |
| OK for CofC | 5/18/2020 | MARK FERRARI |
| CofC Issued | 5/26/2020 | DAVID TSAU |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 12/5/2019 | GRACIELA ACOSTA |
| ZI | Cleared | 12/5/2019 | GRACIELA ACOSTA |
| Housing rent stabilization | Cleared | 1/15/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Courteous Construction Co Inc; Lic. No.: 567324-B | P O BOX 9287 GLENDALE, CA 91226 |
| Engineer | Rezazadeh,, Mehdi; Lic. No.: C49626 | P O BOX 98 DANVILLE, CA 94526 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2020 | Approved | MARK FERRARI |
| Deputy Reinf. Concrete | 2/5/2020 | Conditional Approval | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 2/6/2020 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 2/6/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 2/6/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 2/6/2020 | Not Ready for Inspection | MARK FERRARI |
| Deputy Reinf. Concrete | 2/7/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 2/11/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 2/18/2020 | Not Ready for Inspection | MARK FERRARI |
| Special/Order Compliance | 2/18/2020 | Approved | LANNY MERRICK |
| Interior/Exterior Lathing | 3/31/2020 | Approved | DARRYL ARNOLD |
| Final | 4/8/2020 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 4/8/2020 | Partial Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 4/8/2020 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 4/8/2020 | Partial Approval | DARRYL ARNOLD |
| Final | 4/23/2020 | Conditional Approval | FELIX CEBALLOS |
| METHANE-Final | 4/23/2020 | Approved | FELIX CEBALLOS |
| Smoke Detectors | 4/23/2020 | Approved | FELIX CEBALLOS |
| Final | 5/18/2020 | OK for CofC | MARK FERRARI |