12415 W ARCHWOOD ST 91606
Certificate Information: 12415 W ARCHWOOD ST 91606
- Application / Permit
- 19016-10000-31717
- Plan Check / Job No.
- B19LA21073
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install new (1) STEEL SPECIAL CANTILEVER COLUMN
- Permit Issued
- Issued on 8/25/2020
- Issuing Office
- Current Status
- CofC Issued on 8/17/2023
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | DANIEL SANJUAN |
| Corrections Issued | 11/27/2019 | DANIEL SANJUAN |
| Quality Review Completed | 12/2/2019 | HANS SANTIAGO |
| Plan Check Approved | 6/11/2020 | DANIEL SANJUAN |
| Issued | 8/25/2020 | APPLICANT |
| OK for CofC | 8/10/2023 | KENNETH ROBERTS |
| CofC Issued | 8/17/2023 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/17/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Kazarians,, Ardashes; Lic. No.: C36687 | 1528 CANADA BLVD STE 206 GLENDALE, CA 91208 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/21/2020 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 9/30/2020 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 10/16/2020 | Approved | EDWIN GREGORYONA |
| Deputy Drilled-In Anchors | 10/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Reinf. Concrete | 10/20/2020 | Partial Approval | EDWIN GREGORYONA |
| Structural Steel Frame | 10/20/2020 | Approved | EDWIN GREGORYONA |
| Wood Frame | 10/20/2020 | Approved | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 10/27/2020 | Approved | EDWIN GREGORYONA |
| Final | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/10/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 6/23/2023 | Corrections Issued | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 6/23/2023 | Approved | KENNETH ROBERTS |
| Final | 8/10/2023 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 8/10/2023 | SGSOV Approved | KENNETH ROBERTS |