7075 W LANEWOOD AVE 90028
Certificate Information: 7075 W LANEWOOD AVE 90028
- Application / Permit
- 19016-10000-31652
- Plan Check / Job No.
- B19LA21027
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (6) SCCS.
- Permit Issued
- Issued on 3/6/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 11/10/2020
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2019 | DANIEL SANJUAN |
| Corrections Issued | 11/7/2019 | DANIEL SANJUAN |
| Quality Review Completed | 11/7/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Plan Check Approved | 1/15/2020 | DANIEL SANJUAN |
| Issued | 3/6/2020 | LADBS |
| OK for CofC | 11/6/2020 | SABAS ALONSO |
| CofC Issued | 11/10/2020 | DAVID TSAU |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 1/9/2020 | GISELLE CORELLA |
| Housing rent stabilization | Cleared | 2/19/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Mae Cm Services; Lic. No.: 886471-B | 6137 WILSHIRE BLVD LOS ANGELES, CA 90048 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 6631 MURIETTA AVE LOS ANGELES, CA 91405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/30/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 5/12/2020 | Corrections Issued | MARK FERRARI |
| Deputy Steel/Welding | 5/18/2020 | Conditional Approval | MARK FERRARI |
| Deputy Steel/Welding | 5/19/2020 | Partial Approval | FELIX CEBALLOS |
| Wood Frame | 6/11/2020 | Conditional Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 6/17/2020 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 6/17/2020 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 6/23/2020 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 6/30/2020 | Partial Approval | FELIX CEBALLOS |
| Footing/Foundation/Slab | 7/1/2020 | Approved | FELIX CEBALLOS |
| Structural Steel Frame | 7/1/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 7/1/2020 | Approved | FELIX CEBALLOS |
| Wood Frame | 7/7/2020 | Corrections Issued | MARK FERRARI |
| Interior/Exterior Lathing | 9/17/2020 | Approved | MARK FERRARI |
| Deputy Fireproofing | 10/5/2020 | Conditional Approval | FRED WOHLFARTH |
| Final | 10/27/2020 | Partial Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 10/27/2020 | SGSOV Not Ready | JONATHAN QUACH |
| Smoke Detectors | 10/27/2020 | Approved | JONATHAN QUACH |
| Final | 11/6/2020 | OK for CofC | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/6/2020 | SGSOV Approved | SABAS ALONSO |