8405 W 1ST ST 90048
Certificate Information: 8405 W 1ST ST 90048
- Application / Permit
- 19016-10000-31612
- Plan Check / Job No.
- B19LA21008
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL 1 OMF.
- Permit Issued
- Issued on 6/11/2021
- Issuing Office
- Current Status
- CofC Issued on 12/20/2021
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | JESSE VIDUYA |
| Corrections Issued | 11/18/2019 | JESSE VIDUYA |
| Quality Review Completed | 11/21/2019 | SAI KHUM |
| Building Plans Picked Up | 11/25/2019 | APPLICANT |
| Plan Check Approved | 1/29/2020 | JESSE VIDUYA |
| Issued | 6/11/2021 | APPLICANT |
| OK for CofC | 12/20/2021 | DARRYL ARNOLD |
| CofC Issued | 12/20/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/8/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Sks Construction; Lic. No.: 720390-B | 15134 FRIAR STREET VAN NUYS, CA 91411 |
| Engineer | Shaolian,, Shahab Joseph; Lic. No.: C84155 | 5104 GARDEN GROVE TARZANA, CA 91356 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/22/2021 | Approved | BRUCE CAMPBELL |
| Deputy Drilled-In Anchors | 6/29/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 6/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 6/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 6/30/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 6/30/2021 | Approved | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/6/2021 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 7/7/2021 | Approved | BRUCE CAMPBELL |
| Final | 11/2/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| METHANE-Final | 11/2/2021 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 11/2/2021 | Conditional Approval | DARRYL ARNOLD |
| Special/Order Compliance | 11/3/2021 | Corrections Issued | DARRYL ARNOLD |
| Final | 12/20/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 12/20/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/20/2021 | Approved | DARRYL ARNOLD |