14842 W FRIAR ST 91411
Certificate Information: 14842 W FRIAR ST 91411
- Application / Permit
- 19016-10000-31364
- Plan Check / Job No.
- B19LA20881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL CANTILEVER COLUMN.
- Permit Issued
- Issued on 7/30/2020
- Issuing Office
- Current Status
- CofC Issued on 11/10/2020
Permit Application Status History
| Submitted | 10/3/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | MANUEL MONTUFAR |
| Corrections Issued | 11/18/2019 | MANUEL MONTUFAR |
| Quality Review Completed | 12/1/2019 | HANS SANTIAGO |
| Plan Check Approved | 6/19/2020 | MANUEL MONTUFAR |
| Issued | 7/30/2020 | APPLICANT |
| OK for CofC | 11/6/2020 | SABAS ALONSO |
| CofC Issued | 11/10/2020 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/27/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Au,, Chi-Ming; Lic. No.: C44491 | 8857 ARDENDALE AVE SAN GABRIEL, CA 91775 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/3/2020 | Partial Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 9/15/2020 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 9/16/2020 | Conditional Approval | DANIEL VARNUM |
| Structural Steel Frame | 9/18/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 9/18/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 9/28/2020 | Approved | DANIEL VARNUM |
| Final | 10/1/2020 | Partial Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 10/1/2020 | Approved | DANIEL VARNUM |
| Final | 11/6/2020 | OK for CofC | SABAS ALONSO |