6664 N WILKINSON AVE 91606
Certificate Information: 6664 N WILKINSON AVE 91606
- Application / Permit
- 19016-10000-31201
- Plan Check / Job No.
- B19LA20794
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan 1111 :: Soft-Story seismic retrofit per LABC Chapter 93: Install new SCCS.
- Permit Issued
- Issued on 4/1/2021
- Issuing Office
- Current Status
- CofC Issued on 12/10/2021
Permit Application Status History
| Submitted | 10/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | DANIEL YIP |
| Corrections Issued | 11/14/2019 | DANIEL YIP |
| Quality Review Completed | 11/24/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 6/10/2020 | DANIEL YIP |
| Applicant returned to address corrections | 8/26/2020 | DANIEL YIP |
| Applicant returned to address corrections | 9/1/2020 | DANIEL YIP |
| Applicant returned to address corrections | 10/20/2020 | DANIEL YIP |
| Plan Check Approved | 11/4/2020 | DANIEL YIP |
| Issued | 4/1/2021 | APPLICANT |
| OK for CofC | 10/20/2021 | KENNETH ROBERTS |
| CofC Issued | 12/10/2021 | KENNETH ROBERTS |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/31/2021 | MICHAEL SOTO |
Contact Information
| Contractor | American Retrofitters Corp; Lic. No.: 1020382-B | 15643 SHERMAN WAY STE 220 VAN NUYS, CA 91406 |
| Engineer | Mouser,, Louis Anthony; Lic. No.: C84994 | 616 MASSELIN AVE 225 LOS ANGELES, CA 90036 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 5/7/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/7/2021 | Approved | JOE VELASQUEZ |
| Deputy Drilled-In Anchors | 5/11/2021 | No Access for Inspection | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/12/2021 | Corrections Issued | JOE VELASQUEZ |
| Footing/Foundation/Slab | 5/14/2021 | Approved | JOE VELASQUEZ |
| Deputy Reinf. Concrete | 5/17/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Reinf. Concrete | 5/18/2021 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 6/10/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 6/10/2021 | No Access for Inspection | JOE VELASQUEZ |
| Structural Steel Frame | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Deputy Steel/Welding | 7/19/2021 | No Access for Inspection | JOE VELASQUEZ |
| Insulation | 7/21/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 7/21/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/12/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Interior/Exterior Lathing | 8/17/2021 | Approved | JOE VELASQUEZ |
| Final | 9/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/16/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 9/16/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 10/20/2021 | OK for CofC | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Approved | KENNETH ROBERTS |
| Smoke Detectors | 10/20/2021 | Approved | KENNETH ROBERTS |