623 N HOBART BLVD 90004
Certificate Information: 623 N HOBART BLVD 90004
- Application / Permit
- 19016-10000-31133
- Plan Check / Job No.
- B19LA20749
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (N) SCCS AND PLYWOOD SHEAR WALL
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 1/12/2021
Permit Application Status History
| Submitted | 9/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/30/2019 | DANIEL YIP |
| Corrections Issued | 11/4/2019 | DANIEL YIP |
| Quality Review Completed | 11/5/2019 | HANS SANTIAGO |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Plan Check Approved | 12/23/2019 | DANIEL YIP |
| Issued | 9/3/2020 | APPLICANT |
| OK for CofC | 1/5/2021 | MARK FERRARI |
| CofC Issued | 1/12/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/31/2020 | MICHAEL SOTO |
Contact Information
| Contractor | Los Angeles Retrofit & Construction Inc; Lic. No.: 1023060-B | 18075 VENTURA BLVD STE #101 ENCINO, CA 91316 |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 | 8730 COSTA VERDE BLVD APT 2348 SAN DIEGO, CA 92122 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/22/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 10/6/2020 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 10/8/2020 | Approved | MARK FERRARI |
| Structural Steel Frame | 10/8/2020 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/9/2020 | Partial Approval | DARRYL ARNOLD |
| Wood Frame | 10/27/2020 | Corrections Issued | MARK FERRARI |
| Deputy Drilled-In Anchors | 10/29/2020 | Conditional Approval | FRED WOHLFARTH |
| Wood Frame | 11/10/2020 | Partial Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 11/24/2020 | Approved | MARK FERRARI |
| Final | 12/30/2020 | Conditional Approval | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 12/30/2020 | Approved | JONATHAN QUACH |
| Final | 1/5/2021 | OK for CofC | MARK FERRARI |