1335 S HOOVER ST 90006
Certificate Information: 1335 S HOOVER ST 90006
- Application / Permit
- 19016-10000-31033
- Plan Check / Job No.
- B19LA20686
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL SPECIAL CANTILEVER COLUMN.
- Permit Issued
- Issued on 3/9/2022
- Issuing Office
- Current Status
- CofC Issued on 11/30/2022
Permit Application Status History
| Submitted | 9/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2019 | DANIEL SANJUAN |
| Corrections Issued | 11/22/2019 | DANIEL SANJUAN |
| Quality Review Completed | 12/2/2019 | HANS SANTIAGO |
| Applicant returned to address corrections | 4/1/2021 | DANIEL SANJUAN |
| Plan Check Approved | 4/8/2021 | DANIEL SANJUAN |
| Issued | 3/9/2022 | APPLICANT |
| OK for CofC | 11/30/2022 | DARRYL ARNOLD |
| CofC Issued | 11/30/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 11/16/2020 | ALBERT TAM |
| Community Plan Implem. Overlay | Cleared | 2/1/2021 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 2/1/2021 | RAFAEL FONTES |
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2021 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 4/7/2021 | RENZ SORIANO |
| Tenant Habitability Plan | Cleared | 2/15/2022 | MICHAEL SOTO |
Contact Information
| Contractor | Ems Build Corporation; Lic. No.: 1080704-B | 7778 VALLE VISTA DR RANCHO CUCAMONGA, CA 91730 |
| Engineer | Lara,, Arath Saude; Lic. No.: NA68626 | , |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/7/2022 | Approved | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 6/9/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 6/9/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/9/2022 | Approved | BRUCE CAMPBELL |
| Deputy Reinf. Concrete | 6/16/2022 | Conditional Approval | ERNESTO CORRAL |
| Insulation | 7/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 7/29/2022 | Conditional Approval | DARRYL ARNOLD |
| Final | 10/24/2022 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 10/24/2022 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 10/24/2022 | Corrections Issued | DARRYL ARNOLD |
| Final | 11/30/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/30/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/30/2022 | Approved | DARRYL ARNOLD |