1850 S MANHATTAN PL 90018

Certificate Information: 1850 S MANHATTAN PL 90018

Application / Permit
19016-10000-31030
Plan Check / Job No.
B19LA20684
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(18) Dance Studio or Academy
Work Description
(1)CHANGE OF USE from "MANUFACTURING/WAREHOUSE" to "DANCE STUDIO/ACADEMY(Occupand load >>300) (2)SECOND FLOOR ADDITION <<see comments>>
Permit Issued
Issued on 7/7/2020
Issuing Office
Metro
Current Status
Issued on 7/7/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 DEAN LEE
Disabled Access Plans Picked Up 10/25/2019 APPLICANT
Corrections Issued 10/31/2019 DEAN LEE
Quality Review Completed 11/12/2019 BILL STUTSMAN
Applicant returned to address corrections 2/5/2020 DEAN LEE
Applicant returned to address corrections 2/25/2020 DEAN LEE
Applicant returned to address corrections 3/11/2020 DEAN LEE
Green Plans Picked Up 4/29/2020 APPLICANT
Building Plans Picked Up 5/1/2020 APPLICANT
Applicant returned to address corrections 5/14/2020 DEAN LEE
Applicant returned to address corrections 5/19/2020 DEAN LEE
Applicant returned to address corrections 5/29/2020 DEAN LEE
Plan Check Approved 6/4/2020 DEAN LEE
Issued 7/7/2020 APPLICANT

Permit Application Clearance Information

CPC Cleared 12/9/2019 ANNA VIDAL
CPC Cleared 12/9/2019 ANNA VIDAL
ZA Case Cleared 12/9/2019 ANNA VIDAL
ZI Cleared 12/9/2019 ANNA VIDAL
Community Plan Implem. Overlay Cleared 1/17/2020 ELAINE LEI
Green Code Cleared 1/17/2020 COLIN LOREDO
Sewer availability Cleared 3/13/2020 ROSA SILVA
Project located in CRA area Cleared 3/26/2020 GRACIELA ACOSTA
"D" conditions Cleared 4/23/2020 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 4/23/2020 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 4/23/2020 LOUIS ORTEGA
Comm Cor/Mini-Mall Cleared 4/23/2020 LOUIS ORTEGA
ZI Cleared 4/23/2020 LOUIS ORTEGA
Community Plan Implem. Overlay Cleared 4/27/2020 PETE EYRE
Low Impact Development Cleared 5/4/2020 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 5/5/2020 ELAINE LEI
DAS Clearance Cleared 5/6/2020 SHINE LIN
Highway dedication Cleared 5/8/2020 ELAINE LEI
Permit Cleared 5/11/2020 ELENA LOPEZ
Roof/Waste drainage to street Cleared 5/11/2020 ELENA LOPEZ
Fire Marshall Fire Life Safety Cleared 5/18/2020 OSCAR SALGADO JR
Address approval Cleared 5/19/2020 THOMAS LANG
Hydrant and Access approval Cleared 5/20/2020 GEORGE SUCHAND
Community Plan Implem. Overlay Cleared 5/26/2020 HELEN JADALI

Contact Information

Contractor Build Group Construction Company Inc; Lic. No.: 1015855-B 700 S FLOWER ST STE 575      LOS ANGELES, CA 90017

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/9/2020 Approved KATY RAMIREZ
Deputy Drilled-In Anchors 7/14/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 7/14/2020 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 7/14/2020 Partial Approval KATY RAMIREZ
METHANE-Barrier 7/14/2020 Approved KATY RAMIREZ
METHANE-Subgrade 7/14/2020 Approved KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 8/5/2020 Partial Inspection KATY RAMIREZ
Grading Pre-Inspection 8/5/2020 Not Ready for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 8/6/2020 Not Ready for Inspection KATY RAMIREZ
Grading Pre-Inspection 8/6/2020 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/5/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 11/18/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 11/18/2020 No Access for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/23/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 12/2/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 12/3/2020 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 12/3/2020 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/23/2020 Conditional Approval KATY RAMIREZ
Masonry Wall/Backfill 12/29/2020 Not Ready for Inspection DANIEL COLLINS
Reinforced Concrete Frame 12/30/2020 Partial Approval TIMOTHY BUXTON
Masonry Wall/Backfill 1/4/2021 Partial Approval DANIEL COLLINS
Masonry Wall/Backfill 1/7/2021 Partial Approval DANIEL COLLINS
Deputy Steel/Welding 4/5/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/6/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/7/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/9/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/12/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/13/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/14/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/15/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 4/16/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/16/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/19/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/20/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/21/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/22/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/23/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/26/2021 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 4/27/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/27/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 4/28/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/28/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 4/29/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/30/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/3/2021 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 5/3/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/4/2021 Approved KATY RAMIREZ
Deputy Reinf. Concrete 5/5/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/5/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/6/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/7/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/10/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/11/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/12/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/13/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 5/14/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/18/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 5/18/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 5/19/2021 Conditional Approval DANIEL COLLINS
Reinforced Concrete Frame 5/19/2021 Partial Approval DANIEL COLLINS
Deputy Reinf. Concrete 5/20/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 5/20/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 5/25/2021 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 5/26/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 5/26/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 6/2/2021 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/3/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/3/2021 Conditional Approval KATY RAMIREZ
Reinforced Concrete Frame 6/3/2021 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 6/4/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/4/2021 Conditional Approval KATY RAMIREZ
Green Building Rough 6/4/2021 Approved KATY RAMIREZ
METHANE-Rough 6/4/2021 Approved KATY RAMIREZ
Structural Steel Frame 6/4/2021 Corrections Issued KATY RAMIREZ
Deputy Drilled-In Anchors 6/10/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 6/10/2021 Conditional Approval KATY RAMIREZ
Pre-Inspection 6/10/2021 Partial Inspection KATY RAMIREZ
Reinforced Concrete Frame 6/10/2021 Not Ready for Inspection KATY RAMIREZ
Drywall Nailing 7/6/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 7/6/2021 No Access for Inspection KATY RAMIREZ
Deputy Steel/Welding 7/12/2021 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 7/14/2021 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 7/15/2021 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 7/19/2021 Partial Approval DANIEL COLLINS
Insulation 7/23/2021 Partial Approval DANIEL COLLINS
Light Gage Steel Frame 7/23/2021 Partial Approval DANIEL COLLINS
Drywall Nailing 7/26/2021 Not Ready for Inspection DANIEL COLLINS
Drywall Nailing 7/28/2021 Partial Approval KATY RAMIREZ
Light Gage Steel Frame 8/12/2021 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 9/2/2021 Partial Approval KATY RAMIREZ
Drywall Nailing 9/10/2021 Partial Approval DANIEL COLLINS
Insulation 9/10/2021 Partial Approval DANIEL COLLINS
Reinforced Masonry Frame 9/14/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 9/15/2021 Conditional Approval KATY RAMIREZ
Deputy Reinf. Masonry 9/17/2021 Conditional Approval TIMOTHY BUXTON
Reinforced Masonry Frame 9/17/2021 Partial Approval KATY RAMIREZ
Insulation 9/21/2021 Approved KATY RAMIREZ
Reinforced Masonry Frame 9/21/2021 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 10/7/2021 Conditional Approval TIMOTHY BUXTON
Deputy Reinf. Concrete 10/7/2021 Conditional Approval TIMOTHY BUXTON
Reinforced Concrete Frame 10/8/2021 Partial Approval RUSSELL BONVOULOIR
T-Bar Ceiling 10/25/2021 Not Ready for Inspection DANIEL COLLINS
Light Gage Steel Frame 11/5/2021 Not Ready for Inspection KATY RAMIREZ
T-Bar Ceiling 11/5/2021 Not Ready for Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/23/2021 Conditional Approval KATY RAMIREZ
Footing/Foundation/Slab 11/23/2021 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 11/24/2021 Conditional Approval TIMOTHY BUXTON
T-Bar Ceiling 12/2/2021 Partial Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/6/2021 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 12/8/2021 Conditional Approval TIMOTHY BUXTON
Deputy Steel/Welding 1/11/2022 Conditional Approval TIMOTHY BUXTON
Pre-Inspection 1/31/2022 Partial Inspection RUSSELL BONVOULOIR
Pre-Inspection 2/23/2022 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 3/31/2022 Conditional Approval KATY RAMIREZ
Drywall Nailing 4/7/2022 Approved KATY RAMIREZ
Final 4/7/2022 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 4/7/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 4/7/2022 Not Ready for Inspection KATY RAMIREZ
Pre-Inspection 4/7/2022 Approved KATY RAMIREZ
Reinforced Masonry Frame 4/7/2022 Not Ready for Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 4/7/2022 SGSOV No Gas KATY RAMIREZ
Smoke Detectors 4/7/2022 Partial Approval KATY RAMIREZ
Structural Steel Frame 4/7/2022 Not Ready for Inspection KATY RAMIREZ
Pre-Inspection 4/15/2022 Not Ready for Inspection KATY RAMIREZ
Final 5/12/2022 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 5/12/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 5/12/2022 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 5/12/2022 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 5/12/2022 Partial Approval KATY RAMIREZ
Structural Steel Frame 5/12/2022 Not Ready for Inspection KATY RAMIREZ
Final 5/16/2022 Partial Inspection KATY RAMIREZ
Footing/Foundation/Slab 5/16/2022 Not Ready for Inspection KATY RAMIREZ
Green Building Final 5/16/2022 Not Ready for Inspection KATY RAMIREZ
Reinforced Masonry Frame 5/16/2022 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 5/16/2022 Not Ready for Inspection KATY RAMIREZ
Structural Steel Frame 5/16/2022 Not Ready for Inspection KATY RAMIREZ