4511 W PROSPECT AVE 90027

Certificate Information: 4511 W PROSPECT AVE 90027

Application / Permit
19016-10000-31023
Plan Check / Job No.
B19LA20677
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN 1088 - Soft-Story seismic retrofit per LABC Chapter 93: INSTALL STEEL CANTILEVER COLUMN AND STEEL MOMENT FRAME.
Permit Issued
Issued on 2/5/2020
Issuing Office
Metro
Current Status
CofC Issued on 12/22/2020

Permit Application Status History

Submitted 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/6/2019 VARAND SARKISIAN
Corrections Issued 11/14/2019 VARAND SARKISIAN
Quality Review Completed 11/24/2019 HANS SANTIAGO
Plan Check Approved 1/31/2020 VARAND SARKISIAN
Issued 2/5/2020 LADBS
OK for CofC 12/18/2020 MARK FERRARI
CofC Issued 12/22/2020 ERNESTO CORRAL

Permit Application Clearance Information

Tenant Habitability Plan Cleared 2/5/2020 MICHAEL GREGERSON

Contact Information

Contractor Retrofitting360 Inc; Lic. No.: 1039226-B 19562 VENTURA BLVD# 230      TARZANA, CA 91356
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 9/28/2020 Conditional Approval FRED WOHLFARTH
Pre-Inspection 10/1/2020 Corrections Issued MARK FERRARI
Deputy Steel/Welding 10/5/2020 Conditional Approval FRED WOHLFARTH
Deputy Drilled-In Anchors 11/9/2020 Conditional Approval JONATHAN QUACH
Footing/Foundation/Slab 11/13/2020 Approved JONATHAN QUACH
Reinforced Concrete Frame 11/13/2020 Partial Approval JONATHAN QUACH
Structural Steel Frame 11/13/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 11/13/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 11/19/2020 Partial Inspection MARK FERRARI
Structural Steel Frame 11/19/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 11/19/2020 Partial Approval MARK FERRARI
Reinforced Concrete Frame 11/24/2020 No Access for Inspection MARK FERRARI
Structural Steel Frame 11/24/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 11/24/2020 Not Ready for Inspection MARK FERRARI
Reinforced Concrete Frame 11/25/2020 Not Ready for Inspection JONATHAN QUACH
Structural Steel Frame 11/25/2020 Corrections Issued JONATHAN QUACH
Wood Frame 11/25/2020 Not Ready for Inspection JONATHAN QUACH
Reinforced Concrete Frame 12/3/2020 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 12/3/2020 Not Ready for Inspection MARK FERRARI
Wood Frame 12/3/2020 Approved MARK FERRARI
Interior/Exterior Lathing 12/11/2020 Partial Inspection JONATHAN QUACH
Final 12/18/2020 OK for CofC MARK FERRARI
SGSOV-Seismic Gas S/O Valve 12/18/2020 SGSOV Approved MARK FERRARI
Smoke Detectors 12/18/2020 Approved MARK FERRARI