5126 E MARTIN ST 90032
Certificate Information: 5126 E MARTIN ST 90032
- Application / Permit
- 19016-10000-30953
- Plan Check / Job No.
- B19LA20634
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 SPECIAL CANTILEVERED COLUMN SYSTEM (SCCS) WITH CONCRETE GRADE BEAM. WORKS AT TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
- Permit Issued
- Issued on 4/8/2020
- Issuing Office
- Current Status
- CofC Issued on 8/18/2020
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | ERWIN PASCUA |
| Corrections Issued | 11/9/2019 | ERWIN PASCUA |
| Quality Review Completed | 11/18/2019 | SAI KHUM |
| Building Plans Picked Up | 11/21/2019 | APPLICANT |
| Plan Check Approved | 1/7/2020 | ERWIN PASCUA |
| Issued | 4/8/2020 | APPLICANT |
| OK for CofC | 8/12/2020 | MARK FERRARI |
| CofC Issued | 8/18/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/12/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Courteous Construction Co Inc; Lic. No.: 567324-B | P O BOX 9287 GLENDALE, CA 91226 |
| Engineer | Rezazadeh,, Mehdi; Lic. No.: C49626 | P O BOX 98 DANVILLE, CA 94526 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/19/2020 | Partial Approval | MARK FERRARI |
| Deputy Steel/Welding | 5/26/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 6/3/2020 | Not Ready for Inspection | MARK FERRARI |
| Excavation/Setback/Form/Re-Bar | 6/4/2020 | Approved | MARK FERRARI |
| Wood Frame | 6/4/2020 | Partial Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 6/5/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 6/12/2020 | Conditional Approval | VAHE KELEDJIAN |
| Wood Frame | 6/16/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 6/19/2020 | Approved | MARK FERRARI |
| Final | 7/2/2020 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 7/2/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 7/2/2020 | Approved | MARK FERRARI |
| Final | 8/12/2020 | OK for CofC | MARK FERRARI |