2010 E 15TH ST 90021

Certificate Information: 2010 E 15TH ST 90021

Application / Permit
19016-10000-30938
Plan Check / Job No.
B19LA20621
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
TENANT IMPROVEMENT FOR INTERIOR DEMOLITION OF NON BEARING WALLS AND INSTALLATION OF NEW INTERIOR WALLS. NEW ACCESSIBLE RESTROOMS & PARKING STALLS. NEW OPENING IN EXISTING EXTERIOR CONCRETE WALL. PARTIAL CHANGE OF USE FROM OFFICE TO WAREHOUSE.
Permit Issued
Issued on 5/12/2020
Issuing Office
West Los Angeles
Current Status
Issued on 5/12/2020
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 SAMUEL GONZALEZ
Corrections Issued 10/17/2019 SAMUEL GONZALEZ
Quality Review Completed 10/24/2019 QUAN NGHIEM
Building Plans Picked Up 10/31/2019 APPLICANT
Disabled Access Plans Picked Up 11/12/2019 APPLICANT
Plan Check Approved 1/31/2020 SAMUEL GONZALEZ
Issued 5/12/2020 LADBS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/5/2019 ERIK BEASLEY
Sewer availability Cleared 11/5/2019 ERIK BEASLEY
DAS Clearance Cleared 1/14/2020 ELIZABETH TOMS

Contact Information

Architect Simon,, Matthew Evans; Lic. No.: C29326 3956 GUNDRY AVENUE      LONG BEACH, CA 90807
Contractor A B F American Construction Group Inc; Lic. No.: 1055862-B 6913 WHITE OAK AVENUE      RESEDA, CA 91335
Engineer Bushra,, Rafeek L; Lic. No.: S4490 2564 W WOODLAND DR      ANAHEIM, CA 92801

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Light Gage Steel Frame 6/8/2020 Partial Inspection KATY RAMIREZ
Pre-Inspection 6/8/2020 Approved KATY RAMIREZ
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval JONATHAN QUACH
Insulation 6/22/2020 Approved JONATHAN QUACH
Drywall Nailing 7/14/2020 Partial Approval LANNY MERRICK
Pre-Inspection 7/31/2020 Partial Inspection LANNY MERRICK
Drywall Nailing 10/29/2020 Approved LANNY MERRICK
Drywall Nailing 1/25/2021 Partial Approval RONALD PACHECO
Final 10/1/2021 Partial Inspection JONATHAN QUACH
Pre-Inspection 10/1/2021 Approved JONATHAN QUACH
Special/Order Compliance 5/11/2026 Corrections Issued SEAN POMISH
Order to Comply 5/12/2026 Not Required SEAN POMISH