1340 S MAIN ST 90291
Certificate Information: 1340 S MAIN ST 90291
- Application / Permit
- 19016-10000-30897
- Plan Check / Job No.
- B19LA20597
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV.93 INSTALLING 2 (N) OMF. UPGRADE EXISTING RESTROOM IN THE COMMERCIAL TENANT SPACE FOR ACCESSIBILITY.
- Permit Issued
- Issued on 9/11/2020
- Issuing Office
- Current Status
- CofC Issued on 4/12/2022
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | ALBERT SERVIN |
| Corrections Issued | 11/12/2019 | ALBERT SERVIN |
| Quality Review Completed | 11/14/2019 | KEN GILL |
| Building Plans Picked Up | 11/19/2019 | APPLICANT |
| Applicant returned to address corrections | 6/4/2020 | ALBERT SERVIN |
| Plan Check Approved | 8/25/2020 | ALBERT SERVIN |
| Issued | 9/11/2020 | APPLICANT |
| OK for CofC | 4/11/2022 | GRANT WOODS |
| CofC Issued | 4/12/2022 | DAVID TSAU |
Permit Application Clearance Information
| Historic monument | Cleared | 6/19/2020 | LAMBERT GIESSINGER |
| DAS Clearance | Cleared | 8/25/2020 | ALBERT SERVIN |
| Housing rent stabilization | Cleared | 9/9/2020 | MICHAEL SOTO |
Contact Information
| Contractor | U S Prime Contractor Inc; Lic. No.: 870656-B | 30011 IVY GLENN DR STE 204 LAGUNA NIGUEL, CA 92677 |
| Engineer | Vahdani-Sanavi,, Behruz; Lic. No.: C35605 | 28570 MARGUERITE PKWY STE 204 MISSION VIEJO, CA 92692 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/9/2020 | Approved | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 10/20/2020 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/23/2020 | Partial Approval | GRANT WOODS |
| Deputy Steel/Welding | 10/26/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 11/19/2020 | Partial Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 12/3/2020 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 12/8/2020 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 12/11/2020 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 12/11/2020 | Approved | GRANT WOODS |
| Final | 2/2/2021 | Not Ready for Inspection | GRANT WOODS |
| METHANE-Final | 2/2/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 2/2/2021 | Not Ready for Inspection | GRANT WOODS |
| Final | 4/11/2022 | OK for CofC | GRANT WOODS |
| Smoke Detectors | 4/11/2022 | Approved | GRANT WOODS |