913 W 48TH ST 90037
Certificate Information: 913 W 48TH ST 90037
- Application / Permit
- 19016-10000-30850
- Plan Check / Job No.
- B19LA20563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- GARAGE CONVERSION TO ACCESSORY DWELLING UNIT PER AB494 & SB229 W/ ADDITION (12'-6" X 15'-0") "COMPLY WITH DEPARTMENT ORDER effective date 01/04/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 11/12/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2019 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 9/27/2019 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 11/12/2019 | SINA KHOSRAVI |
| Issued | 11/12/2019 | LADBS |
| CofO in Progress | 11/19/2020 | ROBERT MCDOWELL |
| Permit Finaled | 4/27/2021 | DEROLD HAUFF |
| CofO Issued | 4/27/2021 | DEROLD HAUFF |
| Permit Finaled | 4/27/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/27/2019 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 9/27/2019 | JEANETTE VONG |
| ZI | Cleared | 9/27/2019 | TERRI OSBORNE |
| Eng Process Fee Ord 176,300 | Cleared | 10/1/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 10/1/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Rough | 7/16/2020 | Approved | ROBERT MCDOWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/16/2020 | Corrections Issued | ROBERT MCDOWELL |
| Insulation | 7/27/2020 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 7/27/2020 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/31/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Rough | 7/31/2020 | Approved | ROBERT MCDOWELL |
| Drywall Nailing | 8/6/2020 | Approved | SABAS ALONSO |
| Green Building Rough | 8/6/2020 | Approved | SABAS ALONSO |
| Shower Pan | 8/28/2020 | Corrections Issued | SABAS ALONSO |
| Special/Order Compliance | 8/28/2020 | Corrections Issued | HORACE FULTZ |
| Interior/Exterior Lathing | 9/3/2020 | Approved | ROBERT MCDOWELL |
| ELECTRICAL-Final | 11/19/2020 | Approved | ROBERT MCDOWELL |
| Final | 11/19/2020 | OK to Issue CofO | ROBERT MCDOWELL |
| Green Building Final | 11/19/2020 | Approved | ROBERT MCDOWELL |
| HVAC-Final | 11/19/2020 | Approved | ROBERT MCDOWELL |
| PLUMBING-Final | 11/19/2020 | Approved | ROBERT MCDOWELL |
| SGSOV-Seismic Gas S/O Valve | 11/19/2020 | SGSOV Approved | ROBERT MCDOWELL |
| Smoke Detectors | 11/19/2020 | Approved | ROBERT MCDOWELL |
| Special/Order Compliance | 3/19/2021 | Corrections Issued | SABAS ALONSO |