1456 S BROCKTON AVE 90025
Certificate Information: 1456 S BROCKTON AVE 90025
- Application / Permit
- 19016-10000-30651
- Plan Check / Job No.
- B19LA20420
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV.93 INSTALLING (3) SCCS
- Permit Issued
- Issued on 6/14/2021
- Issuing Office
- Current Status
- CofC Issued on 8/23/2021
Permit Application Status History
| Submitted | 9/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | ARMEN JIVALAGIAN |
| Corrections Issued | 11/12/2019 | ARMEN JIVALAGIAN |
| Quality Review Completed | 11/14/2019 | SAI KHUM |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Plan Check Approved | 12/5/2019 | ARMEN JIVALAGIAN |
| Issued | 6/14/2021 | APPLICANT |
| OK for CofC | 8/16/2021 | JOHN DODGE |
| CofC Issued | 8/23/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 6/8/2021 | MICHAEL SOTO |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/18/2021 | Corrections Issued | GRANT WOODS |
| Wood Frame | 7/8/2021 | Partial Approval | JOHN DODGE |
| Deputy Drilled-In Anchors | 7/19/2021 | Conditional Approval | GRANT WOODS |
| Deputy Steel/Welding | 7/20/2021 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 7/20/2021 | Approved | GRANT WOODS |
| Structural Steel Frame | 7/20/2021 | Not Ready for Inspection | GRANT WOODS |
| Wood Frame | 7/20/2021 | Not Ready for Inspection | GRANT WOODS |
| Structural Steel Frame | 7/23/2021 | Approved | JOHN DODGE |
| Wood Frame | 7/23/2021 | Conditional Approval | JOHN DODGE |
| Insulation | 7/26/2021 | Approved | ALAN NOVAK |
| Interior/Exterior Lathing | 7/27/2021 | Approved | ALAN NOVAK |
| Final | 8/12/2021 | Not Ready for Inspection | JOHN DODGE |
| SGSOV-Seismic Gas S/O Valve | 8/12/2021 | SGSOV Approved | JOHN DODGE |
| Smoke Detectors | 8/12/2021 | Approved | JOHN DODGE |
| Final | 8/16/2021 | OK for CofC | JOHN DODGE |