4924 E NAVARRO ST 90032
Certificate Information: 4924 E NAVARRO ST 90032
- Application / Permit
- 19016-10000-30472
- Plan Check / Job No.
- B19LA20280
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story seismic retrofit per LAMC division 93. (3) New single-story steel cantilevered columns (SCCS).
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofC Issued on 5/11/2021
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | RODOLFO ARIAS |
| Corrections Issued | 11/13/2019 | RODOLFO ARIAS |
| Quality Review Completed | 11/13/2019 | KEN GILL |
| Building Plans Picked Up | 11/18/2019 | APPLICANT |
| Applicant returned to address corrections | 2/7/2020 | RODOLFO ARIAS |
| Plan Check Approved | 3/17/2020 | RODOLFO ARIAS |
| Issued | 9/30/2020 | APPLICANT |
| OK for CofC | 4/26/2021 | MARK FERRARI |
| CofC Issued | 5/11/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 9/18/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Caribe Construction Inc; Lic. No.: 878090-B | 521 PARISH PLACE BURBANK, CA 91506 |
| Engineer | Morales,, Cesar Del Valle; Lic. No.: C76612 | 370 S COMMONWEALTH AVENUE #105 LOS ANGELES, CA 90020 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/23/2020 | Approved | MARK FERRARI |
| Deputy Drilled-In Anchors | 12/10/2020 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/10/2020 | Approved | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 12/14/2020 | Conditional Approval | MARK FERRARI |
| Wood Frame | 1/21/2021 | Partial Approval | MARK FERRARI |
| Wood Frame | 2/24/2021 | Partial Approval | MARK FERRARI |
| Deputy Wood Construction | 3/1/2021 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 3/16/2021 | Corrections Issued | MARK FERRARI |
| Final | 4/14/2021 | Conditional Approval | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 4/14/2021 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 4/14/2021 | Approved | MARK FERRARI |
| Final | 4/26/2021 | OK for CofC | MARK FERRARI |